Geneville Constructions Pty Ltd v Leslight (No 2) [2019] NSWDC 172
The Court found that the parties made a cost-plus agreement on 20 March 2012 under which Geneville was engaged for the project, with a 15% profit component and progress claims payable within seven days, but the agreement was unenforceable by Geneville under s 10 of the Home Building Act 1989 (NSW) because it was not a written residential building contract satisfying s 7. Geneville was nevertheless entitled to recover on a quantum meruit because Mr Leslight received and accepted the benefit of the work and it would be unconscionable for him to retain that benefit without payment. The defendant's cross-claim failed because the alleged defects, over-excavation, unnecessary works and delays...
- Jurisdiction
- Australia
- Judgment Date
- 09 May 2019
- Procedural Posture
- Civil Building and Construction Proceedings Involving a Claim for Payment Under an Alleged Contract or Alternatively Quantum Meruit, and a Cross Claim for Alleged Defects, Delay and Other Losses / Principal Judgment After Trial and Adoption of Referee Report
- Outcome
- Judgment for the plaintiff in the Statement of Claim proceedings; the Cross-Claim is dismissed.
- Legal Topics
- ['absence of Formal Written Residential Building Contract' 'home Building Act 1989 (nsw) Ss 7 and 10' 'cost Plus Building Arrangement' 'unenforceable Residential Building Contract' 'quantum Meruit for Building Work' 'delay and Defects Cross Claim' 'referee Report Under Uniform Civil Procedure Rules 2005' 'witness Credibility']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil Building and Construction Proceedings Involving a Claim for Payment Under an Alleged Contract or Alternatively Quantum Meruit, and a Cross Claim for Alleged Defects, Delay and Other Losses / Principal Judgment After Trial and Adoption of Referee Report
Legal Issues
- 1 ['What agreement was made between Geneville Constructions Pty Ltd and Brett Barry Leslight and what were its terms' 'Whether the agreement was enforceable given ss 7 and 10 of the Home Building Act 1989 (NSW)' 'Whether Geneville Constructions Pty Ltd was entitled to recover the value of work on a quantum meruit basis if the contract was unenforceable' 'Whether the defendant established his cross-claim for alleged unnecessary works, defective works, over-excavation, poor workmanship and delay losses' 'Whether alleged delay losses were caused by Geneville Constructions Pty Ltd and were recoverable']
Ratio Decidendi
The Court found that the parties made a cost-plus agreement on 20 March 2012 under which Geneville was engaged for the project, with a 15% profit component and progress claims payable within seven days, but the agreement was unenforceable by Geneville under s 10 of the Home Building Act 1989 (NSW) because it was not a written residential building contract satisfying s 7. Geneville was nevertheless entitled to recover on a quantum meruit because Mr Leslight received and accepted the benefit of the work and it would be unconscionable for him to retain that benefit without payment. The defendant's cross-claim failed because the alleged defects, over-excavation, unnecessary works and delays...
Court Disposition
Judgment for the plaintiff in the Statement of Claim proceedings; the Cross-Claim is dismissed.
Orders
- ['Judgment for the plaintiff in the Statement of Claim proceedings.' 'The Cross-Claim is dismissed;' "The defendant is to pay the plaintiff's costs of the proceedings as agreed or assessed;" 'Liberty to the parties to apply within 21 days for a variation of the order in (3) above;' 'The parties are to bring in...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment