Acciona Infrastructure Australia Pty Ltd v Zurich Australian Insurance Limited [2023] FCAFC 47
Exclusion 3.12 was concerned with whether loss or damage to earthwork materials or pavement materials caused by rain was due to an unusually intense rainfall event. The logical and businesslike operation of the clause required the intensity of that rainfall to be assessed by reference to a weather station proximate to the place where the damage was sustained, not a potentially distant point on the Project Site. The text, context and use of the more specific expression "location insured", rather than "Project Site" or "situation", supported construing it as the place within the Project Site where the loss or damage in respect of which the claim is made occurred.
- Jurisdiction
- Australia
- Judgment Date
- 28 March 2023
- Procedural Posture
- Insurance Policy Construction Dispute Concerning a Separate Question / Determination by the Full Court of a Question Referred by Direction of the Chief Justice Pursuant to S 20(1 A) of the Federal Court of Australia Act 1976 (cth)
- Outcome
- Declaration made in favour of the Insurers on the separate question; applicants ordered to pay the respondents' costs of the determination of the separate question.
- Legal Topics
- ['construction and Interpretation of Insurance Policy' 'meaning of "location Insured"' 'construction Risks Material Damage Project Insurance Policy' 'rainfall Exclusion and Exception' 'separate Question']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Insurance Policy Construction Dispute Concerning a Separate Question / Determination by the Full Court of a Question Referred by Direction of the Chief Justice Pursuant to S 20(1 A) of the Federal Court of Australia Act 1976 (cth)
Legal Issues
- 1 ['Whether the expression "location insured" in Exclusion 3.12 meant the whole Project Site or the place where the insured loss or damage occurred.' 'Whether the exception to the exclusion for rain damage to earthwork materials and pavement materials was to be assessed by reference to the weather station nearest to the Project Site or nearest to the location of the damage.']
Ratio Decidendi
Exclusion 3.12 was concerned with whether loss or damage to earthwork materials or pavement materials caused by rain was due to an unusually intense rainfall event. The logical and businesslike operation of the clause required the intensity of that rainfall to be assessed by reference to a weather station proximate to the place where the damage was sustained, not a potentially distant point on the Project Site. The text, context and use of the more specific expression "location insured", rather than "Project Site" or "situation", supported construing it as the place within the Project Site where the loss or damage in respect of which the claim is made occurred.
Court Disposition
Declaration made in favour of the Insurers on the separate question; applicants ordered to pay the respondents' costs of the determination of the separate question.
Orders
- ['It is declared that, on its proper construction, the term "location insured" as it appears in Exclusion 3.12 of a written policy of insurance dated 27 June 2014 issued by the respondents to the Named Insured being Roads and Maritime Services means the location of the loss or damage caused by the event referred to...
Full Case Text
Judgment text and source record