Simpson and Pritchard v Steward & Steward [2011] NSWSC 491
The contract was not a costs plus contract with a cap: the evidence of an oral cap was not accepted, the contractual documents and handwritten warning stated that the contract price was not known and that it was a costs plus contract, and the figure of $467,318.07 was used to calculate the deposit rather than to impose a ceiling. ASB Constructions was not shown to have breached the contractual timing obligation because the 27-week period ran from commencement after the construction certificate, and the later agreement fixed completion by 29 June 2007 subject to an extension. The plaintiffs failed to prove actionable misleading or deceptive conduct causing loss, although Mr Steward...
- Jurisdiction
- Australia
- Judgment Date
- 10 June 2011
- Procedural Posture
- Building and Construction Contract Dispute; Misleading or Deceptive Conduct Claim; Cross Claim for Contract Balance / Principal Judgment After Hearing, With Outstanding Factual and Quantification Issues Referred to an Expert Referee
- Outcome
- The plaintiffs' claims that the contract was capped and that they were entitled to damages for misleading or deceptive conduct or delay failed; unresolved factual and quantification issues were referred to an expert referee, with costs reserved until after the referee's report.
- Legal Topics
- ['construction of Costs Plus Building Contract' 'whether Costs Plus Contract Had a Cap' 'misleading or Deceptive Conduct Under S 42 of the Fair Trading Act 1987' 'residential Building Warranties' 'variations to Building Works' 'reference to Expert Referee']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Building and Construction Contract Dispute; Misleading or Deceptive Conduct Claim; Cross Claim for Contract Balance / Principal Judgment After Hearing, With Outstanding Factual and Quantification Issues Referred to an Expert Referee
Legal Issues
- 1 ['Whether the building contract was a simple costs plus contract or a costs plus contract capped at $467,318.07.' 'Whether ASB Constructions breached express or implied terms concerning time for completion, competitive pricing, consultation, occupation of the premises, variations, workmanship and certification.' 'Whether Mr Steward or ASB Constructions made misleading or deceptive representations before or during the contract.' 'Whether the plaintiffs suffered loss by reason of any representation made.' 'Whether ASB Constructions could recover reasonable remuneration for requested or authorised variations not agreed in writing.' 'Whether outstanding factual issues concerning defects, variations, charges and completion costs should be referred to an expert referee.']
Ratio Decidendi
The contract was not a costs plus contract with a cap: the evidence of an oral cap was not accepted, the contractual documents and handwritten warning stated that the contract price was not known and that it was a costs plus contract, and the figure of $467,318.07 was used to calculate the deposit rather than to impose a ceiling. ASB Constructions was not shown to have breached the contractual timing obligation because the 27-week period ran from commencement after the construction certificate, and the later agreement fixed completion by 29 June 2007 subject to an extension. The plaintiffs failed to prove actionable misleading or deceptive conduct causing loss, although Mr Steward...
Court Disposition
The plaintiffs' claims that the contract was capped and that they were entitled to damages for misleading or deceptive conduct or delay failed; unresolved factual and quantification issues were referred to an expert referee, with costs reserved until after the referee's report.
Orders
- ['The outstanding substantive factual issues identified in paragraph 109 are to be the subject of a reference to an expert referee for determination and quantification.' "The matters for reference include whether the defendants' work, including variations, was defective or not carried out in a proper and workmanlike...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment