Libbesson & anor v Martin & anor [2013] NSWLEC 1242
The court found that s 10(2) was satisfied for Tree 1 and Tree 2 as there was more than a hypothetical possibility of damage caused; however, only the removal of Tree 1 was ordered due to the practicality and extent of required works. Compensation for insurance excess was appropriate as the probability on evidence linked the damage to Tree 2.
- Jurisdiction
- Australia
- Judgment Date
- 24 December 2013
- Procedural Posture
- Trees (disputes Between Neighbours) Act Application / Judgment/principal Judgment
- Outcome
- Application upheld in part
- Legal Topics
- ['damage to Property by Trees' 'compensation for Damage' 'orders for Removal of Trees']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Trees (disputes Between Neighbours) Act Application / Judgment/principal Judgment
Legal Issues
- 1 ["Whether the court's jurisdiction under s 10(2) of the Trees (Disputes Between Neighbours) Act 2006 is engaged for trees causing or likely to cause damage or injury" 'Whether damage to property has been caused or is likely to be caused by trees on neighbouring land' 'Whether pruning or removal of trees is an appropriate remedy' 'Whether compensation should be awarded for insurance excess paid due to damage caused by a tree']
Ratio Decidendi
The court found that s 10(2) was satisfied for Tree 1 and Tree 2 as there was more than a hypothetical possibility of damage caused; however, only the removal of Tree 1 was ordered due to the practicality and extent of required works. Compensation for insurance excess was appropriate as the probability on evidence linked the damage to Tree 2.
Court Disposition
Application upheld in part
Orders
- ['The respondents are to engage and pay for an AQF level 3 arborist to remove Tree 1 (Acacia decurrens) within 60 days.' 'Applicants to provide access for quoting and carrying out works for removal of Tree 1.' 'Works to comply with WorkCover NSW Code of Practice for the Amenity Tree Industry.' 'The respondents are...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment