Raj Saneja and Manju Saneja v Dynabuild Pty Ltd Dynabuild Pty Ltd v Raj Saneja and Manju Saneja [2014] NSWCATCD 84
The Tribunal found that the contract, properly construed in light of the drawings, the KH Standard Specification and surrounding circumstances, included the Ultra Floor system, so the builder's purported Ultra Floor variation was invalid and the homeowners were entitled to reimbursement. Several defects or incomplete items were proven. The builder failed to prove actual delay caused by the homeowners, relying on a theoretical programme and evidence found unreliable, and its post-proceeding variation invoices did not comply with the contractual variation mechanism and were unenforceable. The homeowners were awarded $53,068.00 and the builder's cross claim was dismissed.
- Jurisdiction
- Australia
- Judgment Date
- 27 May 2014
- Procedural Posture
- Home Building Dispute Concerning Residential Building Work Under the Home Building Act 1989 / Principal Judgment After Hearing
- Outcome
- Homeowners' application allowed in the amount of $53,068.00; builder's cross claim dismissed; costs submissions timetable set.
- Legal Topics
- ['defective or Incomplete Residential Building Work' 'contract Variations' 'ultra Floor Slabs' 'delay Damages' 'extension of Time Notices' 'contract Interpretation' 'costs Submissions']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Home Building Dispute Concerning Residential Building Work Under the Home Building Act 1989 / Principal Judgment After Hearing
Legal Issues
- 1 ['Whether and to what extent the alleged defects or incomplete work entitled the homeowners to damages.' 'Whether the cost of the Ultra Floor slabs should have been treated as a variation or borne by the builder as part of the fixed price.' 'Whether and to what extent the homeowners contributed to delay in completion of the dwelling.' 'Whether any contribution to delay amounted to breach of contract causing loss to the builder.' "Whether the builder's later variation invoices were valid and enforceable."]
Ratio Decidendi
The Tribunal found that the contract, properly construed in light of the drawings, the KH Standard Specification and surrounding circumstances, included the Ultra Floor system, so the builder's purported Ultra Floor variation was invalid and the homeowners were entitled to reimbursement. Several defects or incomplete items were proven. The builder failed to prove actual delay caused by the homeowners, relying on a theoretical programme and evidence found unreliable, and its post-proceeding variation invoices did not comply with the contractual variation mechanism and were unenforceable. The homeowners were awarded $53,068.00 and the builder's cross claim was dismissed.
Court Disposition
Homeowners' application allowed in the amount of $53,068.00; builder's cross claim dismissed; costs submissions timetable set.
Orders
- ["On the homeowners' application the builder is ordered to pay to the homeowners the amount of $53,068.00 within 28 days of the date of this order." "The builder's cross claim against the homeowners is dismissed." 'The homeowners submissions on costs, including a detailed assessment of costs setting out the...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment