Avad Construction Group Pty Ltd v Carl La Rocca;; Carl La Rocca v Avad Construction Group Pty Ltd. [2015] NSWCATCD 51
The Tribunal has jurisdiction to determine the Owner's claims as 'building claims' under the Home Building Act 1989, as the claims were sufficiently particularised through expert evidence and Scott Schedule and the Builder was not prejudiced. Most items of defect were determined on the evidence, with the Owner successful only on items where defects were proved and rectification was reasonable. The Builder's counterclaim was established and offset against the Owner's proven entitlement. Claims for 'inconvenience' and certain other items were dismissed for lack of evidence or jurisdiction.
- Jurisdiction
- Australia
- Judgment Date
- 17 April 2015
- Procedural Posture
- Consumer and Commercial Dispute / Final Hearing and Determination
- Outcome
- Application and cross-application partly allowed
- Legal Topics
- ['defective Workmanship' 'building Claims Jurisdiction' 'rectification Costs' 'contract Variations' 'statutory Warranties']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Consumer and Commercial Dispute / Final Hearing and Determination
Legal Issues
- 1 ["Whether the claims made by the Owner constitute 'building claims' under the Home Building Act 1989" 'Whether defects alleged by the Owner were established on the evidence' 'Whether rectification or compensation was appropriate for defects' 'Whether the Builder was entitled to the outstanding contract sum' 'Appropriate calculation of the rectification costs according to evidence and legal principle']
Ratio Decidendi
The Tribunal has jurisdiction to determine the Owner's claims as 'building claims' under the Home Building Act 1989, as the claims were sufficiently particularised through expert evidence and Scott Schedule and the Builder was not prejudiced. Most items of defect were determined on the evidence, with the Owner successful only on items where defects were proved and rectification was reasonable. The Builder's counterclaim was established and offset against the Owner's proven entitlement. Claims for 'inconvenience' and certain other items were dismissed for lack of evidence or jurisdiction.
Court Disposition
Application and cross-application partly allowed
Orders
- ['In matter number HB 14/21880, Avad Construction Group Pty Ltd is to pay Carl La Rocca the sum of $17,641.80 less the sum of $6,329.00 owing to Avad Construction Pty Ltd in HB 14/15525, being a net amount of $11,312.80 within 60 days of the date of these orders.' 'In matter number HB 14/15525, the amount owing to...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment