G&S Engineering Services Pty Ltd v MACH Energy Australia Pty Ltd (No 14) [2024] NSWSC 747

G&S Engineering Services Pty Ltd v MACH Energy Australia Pty Ltd (No 14) [2024] NSWSC 747

CDJV (the discovering party) is to be given the option: to serve affidavits outlining steps taken in relation to relevant discovery issues by a specified deadline, failing which the deponents of affidavits of discovery (Mr Hickman and Ms Hawkins) will be made available for cross-examination limited to those issues. This process accords with the governing principles limiting cross-examination to appropriate cases and provides the discovering party a fair opportunity to address outstanding concerns regarding its discovery process.

Parties
First Plaintiff/cross Defendant/respondent: G&S Engineering Services Pty Ltd; Second Plaintiff/cross Defendant/respondent: DRA Pacific Pty Ltd; Third Cross Defendant/respondent: DRA Group Holdings (Pty) Ltd; Fourth Cross Defendant/respondent: DRA Global Limited; First Defendant/cross Claimant/applicant: MACH Energy Australia Pty Ltd; Second Defendant/cross Claimant/applicant: MACH Mount Pleasant Operations Pty Ltd; Third Defendant/cross Claimant/applicant: J.C.D. Australia Pty Ltd
Jurisdiction
Australia
Judgment Date
18 June 2024
Procedural Posture
Procedural Ruling/interlocutory Judgment / Interlocutory/pre Trial
Outcome
Discovering party to have option to file further affidavits or permit cross-examination on limited issues; matter stood over for compliance or orders.
Legal Topics
Discovery, Affidavits of Discovery, Cross Examination

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 7 Party arguments 2
Sign in to unlock

Parties

G&S Engineering Services Pty Ltd

First Plaintiff/cross Defendant/respondent

DRA Pacific Pty Ltd

Second Plaintiff/cross Defendant/respondent

DRA Group Holdings (Pty) Ltd

Third Cross Defendant/respondent

DRA Global Limited

Fourth Cross Defendant/respondent

MACH Energy Australia Pty Ltd

First Defendant/cross Claimant/applicant

MACH Mount Pleasant Operations Pty Ltd

Second Defendant/cross Claimant/applicant

J.C.D. Australia Pty Ltd

Third Defendant/cross Claimant/applicant

Procedural Posture

Procedural Ruling/interlocutory Judgment / Interlocutory/pre Trial

  1. 1 Whether deponents of affidavits of discovery should be made available for cross-examination
  2. 2 Whether discovering party complied with discovery obligations relating to employees' devices
  3. 3 Adequacy of searches for discoverable material

Ratio Decidendi

CDJV (the discovering party) is to be given the option: to serve affidavits outlining steps taken in relation to relevant discovery issues by a specified deadline, failing which the deponents of affidavits of discovery (Mr Hickman and Ms Hawkins) will be made available for cross-examination limited to those issues. This process accords with the governing principles limiting cross-examination to appropriate cases and provides the discovering party a fair opportunity to address outstanding concerns regarding its discovery process.

Court Disposition

Discovering party to have option to file further affidavits or permit cross-examination on limited issues; matter stood over for compliance or orders.

Orders

  • CDJV may serve affidavits by Mr Hickman and/or Ms Hawkins, setting out steps taken on identified discovery issues, by 5pm on 20 June 2024.
  • If affidavits are not served, Mr Hickman and Ms Hawkins to be made available for cross-examination on specific topics.