Winau Australia Pty Ltd v LCC Property Developments Pty Ltd [2024] NSWSC 209
A gross sum costs order was warranted because the respondents were offshore parties, had conducted the proceedings in a delayed and unsatisfactory manner culminating in dismissal for want of prosecution, were likely to delay or not cooperate in any costs assessment, there was real doubt as to their capacity to satisfy costs, LCC's costs were caused by the respondents' conduct, and the detailed unchallenged expert costs evidence established that the amounts claimed were fair and reasonable without any further discount.
- Jurisdiction
- Australia
- Judgment Date
- 01 March 2024
- Procedural Posture
- Costs Application / Notice of Motion for Gross Sum Costs Order After Proceedings Dismissed for Want of Prosecution
- Outcome
- Gross sum costs order made
- Legal Topics
- ['gross Sum Costs Order' 'costs Assessment' 'dismissal for Want of Prosecution' 'security for Costs']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Costs Application / Notice of Motion for Gross Sum Costs Order After Proceedings Dismissed for Want of Prosecution
Legal Issues
- 1 ["Whether the first defendant's costs should be assessed by the Court as a gross sum pursuant to section 98(4)(c) of the Civil Procedure Act 2005 (NSW)." 'Whether the amount claimed by the first defendant was fair and reasonable on the evidence.' 'Whether any further discount should be applied in making a gross sum costs order.']
Ratio Decidendi
A gross sum costs order was warranted because the respondents were offshore parties, had conducted the proceedings in a delayed and unsatisfactory manner culminating in dismissal for want of prosecution, were likely to delay or not cooperate in any costs assessment, there was real doubt as to their capacity to satisfy costs, LCC's costs were caused by the respondents' conduct, and the detailed unchallenged expert costs evidence established that the amounts claimed were fair and reasonable without any further discount.
Court Disposition
Gross sum costs order made
Orders
- ['Pursuant to section 98(4)(c) of the Civil Procedure Act 2005 (NSW), the liability of the first, second and fourth plaintiffs to the first defendant in respect of the costs orders made on 15 October 2021, 16 September 2022, 11 July 2022, 12 September 2023, 17 October 2023 and 9 November 2023 be fixed in the sum of...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment