Durastyle Homes Pty Ltd v Gosling; Gosling v Durastyle Homes Pty Ltd [2022] NSWCATCD 106

Durastyle Homes Pty Ltd v Gosling; Gosling v Durastyle Homes Pty Ltd [2022] NSWCATCD 106

The Tribunal found that the agreement was a cost plus contract, not a fixed price contract, and the builder was not entitled to further payment or quantum meruit recovery due to lack of evidence supporting fair value of claimed work and non-compliance with statutory insurance requirements. The owners proved certain defective work but could not recover for incomplete works or unproven defects. The builder was ordered to pay $13,994.97 for established defective work and the owners' costs.

Parties
Applicant in HB 21/02359; Respondent in HB 21/14341: Durastyle Homes Pty Ltd; Respondent in HB 21/02359; Applicant in HB 21/14341: Ty Allen Gosling; Respondent in HB 21/02359; Applicant in HB 21/14341: Deanne Vivienne Gosling
Jurisdiction
Australia
Judgment Date
28 June 2022
Procedural Posture
Home Building Claim – Defects and Contractual Dispute / Civil and Administrative Tribunal of NSW (consumer and Commercial Division) – Principal Judgment
Outcome
Builder's application dismissed; owners' application for defective work allowed in part; costs awarded to owners.
Legal Topics
Home Building, Defects Claim, Quantum Meruit, Statutory Warranty, Recovery for Incomplete/defective Work, Costs

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 4 Authorities cited 9 Party arguments 2 Amounts and remedies 2
Sign in to unlock

Parties

Durastyle Homes Pty Ltd

Applicant in HB 21/02359; Respondent in HB 21/14341

Ty Allen Gosling

Respondent in HB 21/02359; Applicant in HB 21/14341

Deanne Vivienne Gosling

Respondent in HB 21/02359; Applicant in HB 21/14341

Procedural Posture

Home Building Claim – Defects and Contractual Dispute / Civil and Administrative Tribunal of NSW (consumer and Commercial Division) – Principal Judgment

  1. 1 Whether the agreement was a cost plus contract or fixed price contract
  2. 2 Entitlement to damages for defective and/or incomplete work under Home Building Act 1989 (NSW)
  3. 3 Builder's entitlement to quantum meruit claim in light of absence of home warranty insurance

Ratio Decidendi

The Tribunal found that the agreement was a cost plus contract, not a fixed price contract, and the builder was not entitled to further payment or quantum meruit recovery due to lack of evidence supporting fair value of claimed work and non-compliance with statutory insurance requirements. The owners proved certain defective work but could not recover for incomplete works or unproven defects. The builder was ordered to pay $13,994.97 for established defective work and the owners' costs.

Court Disposition

Builder's application dismissed; owners' application for defective work allowed in part; costs awarded to owners.

Orders

  • In HB 21/14341 Durastyle Homes Pty Ltd is to pay $13,994.97 to Ty Allen and Deanne Vivienne Gosling immediately.
  • HB 21/02359 is dismissed.