Renbar Constructions Pty Ltd v Sader; Sader v Renbar Constructions Pty Ltd [2022] NSWSC 172

Renbar Constructions Pty Ltd v Sader; Sader v Renbar Constructions Pty Ltd [2022] NSWSC 172

The builder was entitled to payment of the outstanding balance for completed works, based on an implied contractual term since the contract lacked provisions for payment in the absence of compliant progress claims; the owner was entitled to damages for delay and defects, including loss of rental opportunity, and was justified in terminating the contract for serious breach due to delay.

Jurisdiction
Australia
Judgment Date
25 February 2022
Procedural Posture
Building and Construction Contract Dispute / Principal Judgment
Outcome
Builder entitled to payment of balance; owner entitled to damages for delay and defects; parties to confer on final figures and orders.
Legal Topics
['interpretation of Contract Terms' 'implied Terms' 'breach of Contract' 'damages for Delay' 'damages for Defective Work' 'estoppel by Convention']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Building and Construction Contract Dispute / Principal Judgment

  1. 1 ['Whether builder was entitled to recover outstanding balance for construction costs' 'Whether owner was entitled to damages for delay and defects' 'Proper construction and interpretation of progress claim provisions' 'Existence and application of an implied term regarding payment in absence of compliant progress claims' "Whether estoppel by convention applied due to parties' conduct"]

Ratio Decidendi

The builder was entitled to payment of the outstanding balance for completed works, based on an implied contractual term since the contract lacked provisions for payment in the absence of compliant progress claims; the owner was entitled to damages for delay and defects, including loss of rental opportunity, and was justified in terminating the contract for serious breach due to delay.

Court Disposition

Builder entitled to payment of balance; owner entitled to damages for delay and defects; parties to confer on final figures and orders.

Orders

  • ['Builder to be paid unpaid balance of total construction costs as found by expert ($3,266,198.61)' 'Deduction of damages for delay (141 weeks at $820 per week = $115,620)' 'Deduction of damages for loss of rental ($1,600 to $1,625 per week for 141 weeks)' 'Deduction of rectification costs for defects ($27,759 +...