Renbar Constructions Pty Ltd v Sader; Sader v Renbar Constructions Pty Ltd [2022] NSWSC 172
The builder was entitled to payment of the outstanding balance for completed works, based on an implied contractual term since the contract lacked provisions for payment in the absence of compliant progress claims; the owner was entitled to damages for delay and defects, including loss of rental opportunity, and was justified in terminating the contract for serious breach due to delay.
- Jurisdiction
- Australia
- Judgment Date
- 25 February 2022
- Procedural Posture
- Building and Construction Contract Dispute / Principal Judgment
- Outcome
- Builder entitled to payment of balance; owner entitled to damages for delay and defects; parties to confer on final figures and orders.
- Legal Topics
- ['interpretation of Contract Terms' 'implied Terms' 'breach of Contract' 'damages for Delay' 'damages for Defective Work' 'estoppel by Convention']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Building and Construction Contract Dispute / Principal Judgment
Legal Issues
- 1 ['Whether builder was entitled to recover outstanding balance for construction costs' 'Whether owner was entitled to damages for delay and defects' 'Proper construction and interpretation of progress claim provisions' 'Existence and application of an implied term regarding payment in absence of compliant progress claims' "Whether estoppel by convention applied due to parties' conduct"]
Ratio Decidendi
The builder was entitled to payment of the outstanding balance for completed works, based on an implied contractual term since the contract lacked provisions for payment in the absence of compliant progress claims; the owner was entitled to damages for delay and defects, including loss of rental opportunity, and was justified in terminating the contract for serious breach due to delay.
Court Disposition
Builder entitled to payment of balance; owner entitled to damages for delay and defects; parties to confer on final figures and orders.
Orders
- ['Builder to be paid unpaid balance of total construction costs as found by expert ($3,266,198.61)' 'Deduction of damages for delay (141 weeks at $820 per week = $115,620)' 'Deduction of damages for loss of rental ($1,600 to $1,625 per week for 141 weeks)' 'Deduction of rectification costs for defects ($27,759 +...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment