Easter Investment Group Pty Ltd and Anor v E & S Projects Pty Ltd Trading as the Cemento Group & Ors [2023] NSWDC 64
The damage to 1 John Street, including cracking of the slab and damage to the grease trap, was caused by over excavation and lack of underpinning during defendants' demolition works. The Deed imposed joint and several liability on all defendants for such damage, entitling plaintiffs to damages for rectification costs and the unpaid invoice.
- Parties
- First Plaintiff: The Easter Investment Pty Ltd; Second Plaintiff: C.B. Enterprises Int. Pty Ltd; First Defendant: E & S Projects Pty Ltd; Second Defendant: Stephen Fabrizio; Third Defendant: Corus No 1 Pty Ltd; Fourth Defendant: Corus No 2 Pty Ltd; Fifth Defendant: Corus No 3 Pty Ltd; Sixth Defendant: Corus Group Pty Ltd; Seventh Defendant: Cemento Constructions Pty Ltd; Eighth Defendant: Enzo Salsano
- Jurisdiction
- Australia
- Judgment Date
- 22 March 2023
- Procedural Posture
- Civil / Final Judgment After Hearing
- Outcome
- Judgment for the plaintiffs against the defendants jointly and severally
- Legal Topics
- Neighbouring Properties, Excavation, Causation of Damage, Indemnity Under Deed
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
The Easter Investment Pty Ltd
First Plaintiff
C.B. Enterprises Int. Pty Ltd
Second Plaintiff
E & S Projects Pty Ltd
First Defendant
Stephen Fabrizio
Second Defendant
Corus No 1 Pty Ltd
Third Defendant
Corus No 2 Pty Ltd
Fourth Defendant
Corus No 3 Pty Ltd
Fifth Defendant
Corus Group Pty Ltd
Sixth Defendant
Cemento Constructions Pty Ltd
Seventh Defendant
Enzo Salsano
Eighth Defendant
Procedural Posture
Civil / Final Judgment After Hearing
Legal Issues
- 1 Whether damage to 1 John Street, including slab and grease trap, was caused by defendants' demolition and excavation works
- 2 Whether the defendants are liable under the Deed for rectification costs
Ratio Decidendi
The damage to 1 John Street, including cracking of the slab and damage to the grease trap, was caused by over excavation and lack of underpinning during defendants' demolition works. The Deed imposed joint and several liability on all defendants for such damage, entitling plaintiffs to damages for rectification costs and the unpaid invoice.
Court Disposition
Judgment for the plaintiffs against the defendants jointly and severally
Orders
- That there be judgment for the plaintiff against the defendants jointly and severally in the sum of $134,611.
- Interest thereon at the rates pertaining from time to time pursuant to the provisions of section 100 of the Civil Procedure Act
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment