Muriti v Prendergast [2005] NSWSC 922

Muriti v Prendergast [2005] NSWSC 922

The Court determined that the expert's report dated 27 June 2005 should be adopted subject to specified corrections, deletions, and referral of additional questions. The reference is to continue under Part 72 of the Supreme Court Rules 1970 as enabled by transitional provisions. The transfers contemplated by the Heads of Agreement were intended to proceed subject to existing mortgages to the ANZ Banking Group and not be discharged at completion unless otherwise agreed. Further matters may be referred back to the expert as agreed and machinery orders made accordingly.

Jurisdiction
Australia
Judgment Date
13 September 2005
Procedural Posture
Specific Performance and Associated Relief Proceedings / Judgment Following Expert Report and Procedural Applications
Outcome
Expert report adopted subject to variations, deletions, and remittal of further questions. Declaration made as to mortgages. Machinery orders made.
Legal Topics
['reference to Expert' 'enforcement of Contract' 'leases' 'conveyancing' 'transitional Rules' 'mortgages']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Specific Performance and Associated Relief Proceedings / Judgment Following Expert Report and Procedural Applications

  1. 1 ["Whether the expert's report under Part 72 should be adopted with variations" 'Which procedural rules govern—old Supreme Court Rules or Uniform Civil Procedure Rules 2005' 'Proper construction of Heads of Agreement regarding mortgages at completion' 'Whether further questions should be referred back to the expert']

Ratio Decidendi

The Court determined that the expert's report dated 27 June 2005 should be adopted subject to specified corrections, deletions, and referral of additional questions. The reference is to continue under Part 72 of the Supreme Court Rules 1970 as enabled by transitional provisions. The transfers contemplated by the Heads of Agreement were intended to proceed subject to existing mortgages to the ANZ Banking Group and not be discharged at completion unless otherwise agreed. Further matters may be referred back to the expert as agreed and machinery orders made accordingly.

Court Disposition

Expert report adopted subject to variations, deletions, and remittal of further questions. Declaration made as to mortgages. Machinery orders made.

Orders

  • ['The report of Margaret C Hole dated 27 June 2005 is adopted subject to specified corrections (as set out in short minutes) and deletions.' 'Matters as described in short minutes to be referred back to Margaret C Hole pursuant to Part 72 Rule 13 of the Supreme Court Rules 1970 for further expert determination.'...