H & M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd [2021] NSWSC 708

H & M Constructions (NSW) Pty Ltd v Golden Rain Development Pty Ltd [2021] NSWSC 708

The plaintiff is not, in substance, a defendant in the proceedings as it seeks substantive relief for breach of contract and unconscionable conduct. Security for costs is ordered up to mediation, with provision for adjustment if a cross-claim is brought.

Parties
Plaintiff/respondent: H & M Constructions (NSW) Pty Ltd; Defendant/applicant: Golden Rain Development Pty Ltd
Jurisdiction
Australia
Judgment Date
16 June 2021
Procedural Posture
Security for Costs Application / Interlocutory
Outcome
Application for security for costs granted in part.
Legal Topics
Security for Costs, Mediation, Unconscionable Conduct, Breach of Contract

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 3 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

H & M Constructions (NSW) Pty Ltd

Plaintiff/respondent

Golden Rain Development Pty Ltd

Defendant/applicant

Procedural Posture

Security for Costs Application / Interlocutory

  1. 1 Whether the plaintiff should provide security for costs and in what amount
  2. 2 Whether the plaintiff's claim is 'defensive' in nature affecting entitlement to security for costs
  3. 3 Effect of potential cross-claim on security for costs orders

Ratio Decidendi

The plaintiff is not, in substance, a defendant in the proceedings as it seeks substantive relief for breach of contract and unconscionable conduct. Security for costs is ordered up to mediation, with provision for adjustment if a cross-claim is brought.

Court Disposition

Application for security for costs granted in part.

Orders

  • The plaintiff provides security in the sum of $350,000 in respect of the costs of the defendant up to and including the mediation referred to in the Court's orders of 25 May 2021.
  • If the plaintiff fails to pay such security within 14 days of these orders, the proceedings be stayed until the relevant security is provided.