Amflo Constructions Pty Limited v Anthony Jefferies [2003] NSWSC 856
The adjudication application was commenced within time under the Building and Construction Industry Security of Payment Act 1999 because, where a payment schedule is served in response to a section 17(2)(a) notice (after lapse of the initial 10 business days), the applicable timing rule is section 17(3)(e), permitting the application within 10 business days after the end of the 5-day notice period, and this period was complied with by the Subcontractor.
- Parties
- First Plaintiff: Amflo Constructions Pty Limited; Second Plaintiff: George Khouri; First Defendant: Anthony Jefferies; Second Defendant: Westport Plumbing Pty Limited
- Jurisdiction
- Australia
- Judgment Date
- 17 September 2003
- Procedural Posture
- Civil / Judgment After Hearing of Summons
- Outcome
- Summons dismissed
- Legal Topics
- Security of Payment, Statutory Interpretation, Progress Payments, Adjudication Applications, Procedural Time Limits
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Amflo Constructions Pty Limited
First Plaintiff
George Khouri
Second Plaintiff
Anthony Jefferies
First Defendant
Westport Plumbing Pty Limited
Second Defendant
Procedural Posture
Civil / Judgment After Hearing of Summons
Legal Issues
- 1 Whether the adjudication application under the Building and Construction Industry Security of Payment Act 1999 was made within the required time
- 2 Proper construction of sections 14 and 17 of the Building and Construction Industry Security of Payment Act 1999 concerning timing of payment schedules and adjudication applications
Ratio Decidendi
The adjudication application was commenced within time under the Building and Construction Industry Security of Payment Act 1999 because, where a payment schedule is served in response to a section 17(2)(a) notice (after lapse of the initial 10 business days), the applicable timing rule is section 17(3)(e), permitting the application within 10 business days after the end of the 5-day notice period, and this period was complied with by the Subcontractor.
Court Disposition
Summons dismissed
Orders
- Summons dismissed
- Plaintiffs to pay costs of Second Defendant
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment