Ghafoor v Ryte Homes Pty Ltd [2024] NSWSC 370
There was no construction contract between the plaintiffs and Ryte Homes Pty Ltd because the proposed contract did not come into effect until signed by all persons named as Owner and the Builder, and neither the contract nor the tender was signed by two of the owners. The Court also rejected evidence of any separate agreement to pay for tender preparation or any supervision of demolition work. Consequently, no contract or arrangement existed by which Ryte Homes Pty Ltd agreed to perform construction work or supply related goods and services for the plaintiffs, so the adjudicator had no jurisdiction under the Act to adjudicate the payment claim and the determination was void.
- Jurisdiction
- Australia
- Judgment Date
- 11 April 2024
- Procedural Posture
- Application to Have Adjudication Determination Declared Void / Principal Judgment
- Outcome
- Application granted; adjudication determination declared void and ancillary orders made against the first defendant.
- Legal Topics
- ['security of Payment Adjudication' 'construction Contract' 'contract Formation' 'incompleteness' 'executed Contracts']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Application to Have Adjudication Determination Declared Void / Principal Judgment
Legal Issues
- 1 ['Whether the parties had entered a construction contract as defined in s 4(1) of the Building and Construction Industry Security of Payment Act 1999 (NSW).' 'Whether the HIA NSW Residential Building Contract or tender was signed and agreed to by all essential parties.' 'Whether there was any other contract or arrangement under which Ryte Homes Pty Ltd undertook to carry out construction work or supply related goods and services for the plaintiffs.' 'Whether the payment claim was served on the plaintiffs where it was not served on all of them.']
Ratio Decidendi
There was no construction contract between the plaintiffs and Ryte Homes Pty Ltd because the proposed contract did not come into effect until signed by all persons named as Owner and the Builder, and neither the contract nor the tender was signed by two of the owners. The Court also rejected evidence of any separate agreement to pay for tender preparation or any supervision of demolition work. Consequently, no contract or arrangement existed by which Ryte Homes Pty Ltd agreed to perform construction work or supply related goods and services for the plaintiffs, so the adjudicator had no jurisdiction under the Act to adjudicate the payment claim and the determination was void.
Court Disposition
Application granted; adjudication determination declared void and ancillary orders made against the first defendant.
Orders
- ['Declare that the determination of the second defendant issued on 28 November 2023 in respect of Adjudication Application number ABCDRS NSW 561 in favour of the first defendant against the plaintiffs in the amount of $39,725 (the Determination) is void.' 'Order that the first defendant be permanently restrained...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment