Kennedy Civil Contracting Pty Ltd (Administrators Appointed) v Richard Crookes Construction Pty Ltd; In the matter of Kennedy Civil Contracting Pty Ltd (No 2) [2023] NSWSC 248
The court held that costs follow the event on the ordinary basis as the offers of compromise were not found to be genuine, and that a stay of the judgment and certain costs orders was appropriate given the insolvency of the claimant and potential irrecoverability of monies if the appeal succeeded.
- Jurisdiction
- Australia
- Judgment Date
- 21 March 2023
- Procedural Posture
- Civil / Post Judgment, Consequential Orders and Costs
- Outcome
- Judgment for the plaintiff in the Technology & Construction List proceeding (2022/288266) for $719,519.82 including interest; certain motions dismissed; costs made on ordinary basis; stay of certain orders pending filing of notice of appeal. In Corporations Proceeding (2022/353631), leave granted to proceed nunc pro...
- Legal Topics
- ['stay of Proceedings Pending Appeal' 'costs—party/party Basis' 'summary Judgment' 'security of Payment Act—insolvent Claimant' 'offers of Compromise—indemnity Costs']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil / Post Judgment, Consequential Orders and Costs
Legal Issues
- 1 ['Whether an insolvent company subject to a deed of company arrangement can pursue a claim under the Building and Construction Industry Security of Payment Act 1999 (NSW)' 'Whether costs should be awarded on an indemnity or ordinary basis following offers of compromise' 'Whether stay of judgment and costs orders should be granted pending appeal']
Ratio Decidendi
The court held that costs follow the event on the ordinary basis as the offers of compromise were not found to be genuine, and that a stay of the judgment and certain costs orders was appropriate given the insolvency of the claimant and potential irrecoverability of monies if the appeal succeeded.
Court Disposition
Judgment for the plaintiff in the Technology & Construction List proceeding (2022/288266) for $719,519.82 including interest; certain motions dismissed; costs made on ordinary basis; stay of certain orders pending filing of notice of appeal. In Corporations Proceeding (2022/353631), leave granted to proceed nunc pro...
Orders
- ['Notice of motion filed on 9 November 2022 dismissed with no order as to costs (2022/288266)' 'Notice of motion filed on 21 November 2022 dismissed (2022/288266)' 'Judgment for the plaintiff for $719,519.82 including $35,591.33 interest (2022/288266)' 'Defendant to pay plaintiff’s costs of the proceedings on...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment