Guy and Anor v K J & W E McIlveen t/as K J McIlveen Builders [2016] NSWCATCD 77
Because the builder had not complied with the contract's written variation procedure, recovery for variations depended on proof of fair and reasonable remuneration for benefits accepted by the applicants. The Tribunal allowed only those variation amounts established on the evidence, allowed limited rectification and associated costs to the applicants, and allowed delay-related hire costs for 20 weeks where the continued dispute and withholding of keys prevented occupation. The final orders required the applicants to pay the respondent a net sum and each party to bear their own costs.
- Jurisdiction
- Australia
- Judgment Date
- 15 September 2016
- Procedural Posture
- Home Building Dispute in the Consumer and Commercial Division of the Civil and Administrative Tribunal of New South Wales / Principal Judgment After Hearings on 5 April 2016 and 30 June 2016
- Outcome
- Application resolved by monetary order in favour of the respondent builder, with no order for costs beyond each party bearing their own costs.
- Legal Topics
- ['variations Not in Writing' 'quantum Meruit' 'rectification of Defective Works' 'delay Compensation' 'costs']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Home Building Dispute in the Consumer and Commercial Division of the Civil and Administrative Tribunal of New South Wales / Principal Judgment After Hearings on 5 April 2016 and 30 June 2016
Legal Issues
- 1 ['Whether the respondent builder could recover payment for variations where the contractual procedure for written and signed variations had not been complied with.' 'What amount, if any, was recoverable by the builder on a quantum meruit for variation works accepted by the owners.' 'Whether the applicants were entitled to compensation for rectification or completion of defective works.' 'Whether the applicants were entitled to compensation for additional hire costs caused by delay in obtaining occupation or access to the property.']
Ratio Decidendi
Because the builder had not complied with the contract's written variation procedure, recovery for variations depended on proof of fair and reasonable remuneration for benefits accepted by the applicants. The Tribunal allowed only those variation amounts established on the evidence, allowed limited rectification and associated costs to the applicants, and allowed delay-related hire costs for 20 weeks where the continued dispute and withholding of keys prevented occupation. The final orders required the applicants to pay the respondent a net sum and each party to bear their own costs.
Court Disposition
Application resolved by monetary order in favour of the respondent builder, with no order for costs beyond each party bearing their own costs.
Orders
- ['The applicants are to pay the respondent the sum of $5,489.65.' 'Each party is to bear their own costs.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment