A-Tech Australia Pty Ltd v Top Pacific Construction Aust Pty Ltd (No 2) [2019] NSWSC 624

A-Tech Australia Pty Ltd v Top Pacific Construction Aust Pty Ltd (No 2) [2019] NSWSC 624

The Court refused a stay because the defendant's cross-claim raised ordinary disputed factual and quantum issues and there was nothing compelling about it; there was no evidence beyond the plaintiff being a $1 company to show that payment would be practically irrecoverable; and the 7 December consent orders only...

Source-derived case information.

Jurisdiction
Australia
Judgment Date
27 May 2019
Procedural Posture
Building and Construction Payment Claim Under the Building and Construction Industry Security of Payment Act 1999 (nsw); Application for Stay of Enforcement of Judgment / Consequential Orders After Principal Judgment; Ex Tempore Judgment on Final Orders and Stay Application
Outcome
Judgment entered for the plaintiff; defendant's stay application refused; money paid into Court ordered to be paid out to the plaintiff; defendant ordered to pay the plaintiff's costs of the proceedings on its claim.
Legal Topics
['building and Construction Industry Security of Payment Act 1999 (nsw)' 'payment Claims' 'payment Schedules' 'stay of Enforcement' 'money Paid Into Court' 'cross Claim for Breach of Contract' 'costs']
['building and Construction' 'equity Commercial List'] ['building and Construction Industry Security of Payment Act 1999 (nsw)' 'payment Claims' 'payment Schedules' 'stay of Enforcement' 'money Paid Into Court' 'cross Claim for Breach of Contract' 'costs']

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Building and Construction Payment Claim Under the Building and Construction Industry Security of Payment Act 1999 (nsw); Application for Stay of Enforcement of Judgment / Consequential Orders After Principal Judgment; Ex Tempore Judgment on Final Orders and Stay Application

  1. 1 ['Whether judgment should be entered for the plaintiff for the amount due under the Act together with interest.' "Whether enforcement of the judgment should be stayed pending determination of the defendant's cross-claim." 'Whether money previously paid into Court should be paid out to the plaintiff.' "Whether the consent orders made on 7 December prevented the plaintiff from obtaining payment before determination of the defendant's cross-claim." 'Whether evidence that the plaintiff was a $1 company was sufficient to establish a risk that the defendant could not recover payment if its cross-claim later succeeded.']

Ratio Decidendi

The Court refused a stay because the defendant's cross-claim raised ordinary disputed factual and quantum issues and there was nothing compelling about it; there was no evidence beyond the plaintiff being a $1 company to show that payment would be practically irrecoverable; and the 7 December consent orders only compromised an immediate summary judgment application and did not prevent the plaintiff from later obtaining judgment and payment. The plaintiff was therefore entitled to judgment and to payment out of the money in Court.

Court Disposition

Judgment entered for the plaintiff; defendant's stay application refused; money paid into Court ordered to be paid out to the plaintiff; defendant ordered to pay the plaintiff's costs of the proceedings on its claim.

Orders

  • ['Order that judgment be entered in favour of the plaintiff in $487,324.38.' "Order that the defendant's application for a stay of enforcement of the judgment be refused." 'Order that the sum of $466,120.80 paid into Court by the defendant together with any interest accrued on that sum be paid out to the plaintiff.'...