Rathchime Pty Ltd v Willat; Willat v Rathchime [2016] NSWCATCD 74
The Tribunal found that the parties mutually abandoned the contract by July 2013 after an inordinate period in which the builder carried out no work and neither party acted under the contract to require performance or terminate. Because the contract had been abandoned, the homeowners were not entitled to completion costs, but they retained accrued rights for proven defects and statutory warranty breaches. The alleged oral cost savings agreement was not established. The builder was entitled to recover proven variations outside the contract scope on a quantum meruit basis. After setting off $37,130.50 owing to the homeowners for defects against $63,819.03 owing to the builder for...
- Jurisdiction
- Australia
- Judgment Date
- 09 September 2016
- Procedural Posture
- Home Building Claims in the Consumer and Commercial Division of the Civil and Administrative Tribunal of New South Wales / Principal Judgment After Hearing
- Outcome
- The homeowners were ordered to pay the builder $26,688.53 immediately, with costs to be determined on the papers after submissions.
- Legal Topics
- ['abandonment' 'repudiation' 'variations' 'defects' 'statutory Warranties' 'quantum Meruit' 'residential Building Works']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Home Building Claims in the Consumer and Commercial Division of the Civil and Administrative Tribunal of New South Wales / Principal Judgment After Hearing
Legal Issues
- 1 ['Whether the residential building contract came to an end, and if so whether by mutual abandonment, repudiation or termination.' 'Whether the homeowners were entitled to completion costs and damages for defective works.' 'Whether alleged defects breached statutory warranties under the Home Building Act 1989 (NSW).' 'Whether the alleged oral side agreement for cost savings existed and was enforceable.' 'Whether the builder could recover unpaid variations on a quantum meruit basis.']
Ratio Decidendi
The Tribunal found that the parties mutually abandoned the contract by July 2013 after an inordinate period in which the builder carried out no work and neither party acted under the contract to require performance or terminate. Because the contract had been abandoned, the homeowners were not entitled to completion costs, but they retained accrued rights for proven defects and statutory warranty breaches. The alleged oral cost savings agreement was not established. The builder was entitled to recover proven variations outside the contract scope on a quantum meruit basis. After setting off $37,130.50 owing to the homeowners for defects against $63,819.03 owing to the builder for...
Court Disposition
The homeowners were ordered to pay the builder $26,688.53 immediately, with costs to be determined on the papers after submissions.
Orders
- ['The homeowners are to pay the builder the amount of $26,688.53 immediately.' 'The parties are to provide to the Tribunal and each other, either in person or by post, submissions and documents in relation to costs by 15 September 2016.' 'The parties are to provide to the Tribunal and each other, either in person or...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment