Alliance Project Services Pty Ltd v Waverley Council [2023] NSWLEC 1290
The Court upheld the appeal and modified the development control order as agreed by the parties because it was a decision the Court could properly make within its powers under s 8.18(4)(b) of the EPA Act.
- Jurisdiction
- Australia
- Judgment Date
- 09 June 2023
- Procedural Posture
- Appeal / Final Orders After Conciliation Conference
- Outcome
- Appeal upheld; development control order modified in accordance with agreement.
- Legal Topics
- ['development Control Order' 'appeal' 'conciliation Conference' 'modification of Order']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Procedural Posture
Appeal / Final Orders After Conciliation Conference
Legal Issues
- 1 ['Whether the development control order issued on 29 November 2022 ought to be modified pursuant to s 8.18(4)(b) of the Environmental Planning and Assessment Act 1979']
Ratio Decidendi
The Court upheld the appeal and modified the development control order as agreed by the parties because it was a decision the Court could properly make within its powers under s 8.18(4)(b) of the EPA Act.
Court Disposition
Appeal upheld; development control order modified in accordance with agreement.
Orders
- ['The appeal is upheld.' 'The development control order NO-5136 issued on 29 November 2022 is modified in accordance with the development control order at Annexure A.' 'Each party shall pay its own costs.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment