Poche v Ellingworth [2023] NSWSC 889
Leave is granted to the defendant/cross-claimant to file and serve a further amended statement of cross-claim because neither of the pleaded causes of action (damages for breach of collateral contract, or promissory estoppel) are so clearly doomed to fail as to justify summary dismissal or refusal to allow amendment. Difficult questions about the legal maintainability of the collateral contract and use of promissory estoppel as a positive cause of action are not finally determinable at this stage (in particular given the high threshold for summary dismissal and developing law on promissory estoppel). No 'otherwise' costs order is made because to do so could stultify the maintainable claim.
- Parties
- Plaintiff/cross Defendant: Justin Wade Poche; Defendant/cross Claimant: Stephen William Ellingworth
- Jurisdiction
- Australia
- Judgment Date
- 27 July 2023
- Procedural Posture
- Civil / Interlocutory (motions to Amend Cross Claim and for Summary Dismissal)
- Outcome
- Leave granted to amend cross-claim; application for summary dismissal dismissed; costs awarded to defendant/cross-claimant for the motions; case management orders made.
- Legal Topics
- Amendment of Pleadings, Summary Judgment, Collateral Contract, Sale of Land, Promissory Estoppel, Costs Orders
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Justin Wade Poche
Plaintiff/cross Defendant
Stephen William Ellingworth
Defendant/cross Claimant
Procedural Posture
Civil / Interlocutory (motions to Amend Cross Claim and for Summary Dismissal)
Legal Issues
- 1 Whether cross-claimant should be granted leave to file and serve a further amended statement of cross-claim
- 2 Whether plaintiff/cross-defendant's application for summary dismissal of the cross-claim should be granted
- 3 Whether the alleged collateral contract is inconsistent with the formal contract of sale and therefore not legally maintainable
Ratio Decidendi
Leave is granted to the defendant/cross-claimant to file and serve a further amended statement of cross-claim because neither of the pleaded causes of action (damages for breach of collateral contract, or promissory estoppel) are so clearly doomed to fail as to justify summary dismissal or refusal to allow amendment. Difficult questions about the legal maintainability of the collateral contract and use of promissory estoppel as a positive cause of action are not finally determinable at this stage (in particular given the high threshold for summary dismissal and developing law on promissory estoppel). No 'otherwise' costs order is made because to do so could stultify the maintainable claim.
Court Disposition
Leave granted to amend cross-claim; application for summary dismissal dismissed; costs awarded to defendant/cross-claimant for the motions; case management orders made.
Orders
- Leave granted to the defendant/cross-claimant to file and serve the further amended statement of cross-claim in accordance with these reasons by 3 August 2023.
- Plaintiff/cross-defendant's notice of motion of 19 June 2023 is dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment