Piaskowski v Pittwater Council [2015] NSWLEC 1183

Piaskowski v Pittwater Council [2015] NSWLEC 1183

As an agreement under s 34(3) of the Court Act was reached between the parties and was acceptable to the Court, the proceedings must be disposed of in accordance with that agreement, without a merit assessment of the issues.

Parties
Applicant: Andre F Piaskowski; Respondent: Pittwater Council
Jurisdiction
Australia
Judgment Date
26 May 2015
Procedural Posture
Appeal / Conciliation Conference; Final Orders Made
Outcome
Orders made by consent/agreement under s 34(3) of the Land and Environment Court Act 1979
Legal Topics
Building Certificate, Conciliation Conference, Agreement Between the Parties, Orders

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 1
Sign in to unlock

Parties

Andre F Piaskowski

Applicant

Pittwater Council

Respondent

Procedural Posture

Appeal / Conciliation Conference; Final Orders Made

  1. 1 Whether agreement under s 34(3) of the Land and Environment Court Act 1979 is acceptable and can be made as an order of the Court

Ratio Decidendi

As an agreement under s 34(3) of the Court Act was reached between the parties and was acceptable to the Court, the proceedings must be disposed of in accordance with that agreement, without a merit assessment of the issues.

Court Disposition

Orders made by consent/agreement under s 34(3) of the Land and Environment Court Act 1979

Orders

  • Final orders to give effect to the parties' agreement were made on 26 May 2015