Australian Remediation Services v Earth Tech Engineering [2005] NSWSC 715
There is a serious question to be tried regarding the validity of the adjudicator's determination under the Act. The court is satisfied that, conditioned upon the provision of adequate bank guarantees in lieu of payment into court, and undertakings as to damages and expedition, it is appropriate to grant an interlocutory injunction restraining the issue and filing of an adjudication certificate until final hearing or further order.
- Jurisdiction
- Australia
- Judgment Date
- 14 July 2005
- Procedural Posture
- Application for Interlocutory Injunction / Interlocutory (interim Relief)
- Outcome
- Interlocutory injunction granted on conditions
- Legal Topics
- ['adjudication Certificates' 'injunctions' 'security of Payment' 'balance of Convenience']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Application for Interlocutory Injunction / Interlocutory (interim Relief)
Legal Issues
- 1 ['Whether an interlocutory injunction restraining issuance and filing of an adjudication certificate should be granted under the Building and Construction Industry Security of Payment Act 1999' 'Whether the conduct of the adjudicator in seeking further submissions vitiated the determination' 'Appropriate security conditions for the grant of interim injunctive relief']
Ratio Decidendi
There is a serious question to be tried regarding the validity of the adjudicator's determination under the Act. The court is satisfied that, conditioned upon the provision of adequate bank guarantees in lieu of payment into court, and undertakings as to damages and expedition, it is appropriate to grant an interlocutory injunction restraining the issue and filing of an adjudication certificate until final hearing or further order.
Court Disposition
Interlocutory injunction granted on conditions
Orders
- ['Interim injunction restraining the first defendant from requesting an adjudication certificate under s 24(1)(a) of the Building and Construction Industry Security of Payment Act 1999 and from filing any such certificate in Court under s 25, effective until 5 pm on Tuesday 19 July 2005, subject to undertakings as...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment