Baraz Construction Pty Ltd v Strathfield Council [2016] NSWLEC 1287

Baraz Construction Pty Ltd v Strathfield Council [2016] NSWLEC 1287

The court made orders in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979, being satisfied that the decision is one the court could make in the exercise of its functions.

Parties
Applicant: Baraz Construction Pty Ltd; Respondent: Strathfield Council
Jurisdiction
Australia
Judgment Date
12 July 2016
Procedural Posture
Modification Application, Class 1 / Orders Following Conciliation Conference by Consent
Outcome
Appeal upheld; s 96 modification application approved with modified conditions as per Annexures A and B
Legal Topics
Modification Application, Residential Flat Building, Conciliation Conference, Section 34 Agreement

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 1 Party arguments 1
Sign in to unlock

Parties

Baraz Construction Pty Ltd

Applicant

Strathfield Council

Respondent

Procedural Posture

Modification Application, Class 1 / Orders Following Conciliation Conference by Consent

  1. 1 Whether the court should make orders to give effect to the parties' agreement under s 34(3) of the Land and Environment Court Act 1979

Ratio Decidendi

The court made orders in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979, being satisfied that the decision is one the court could make in the exercise of its functions.

Court Disposition

Appeal upheld; s 96 modification application approved with modified conditions as per Annexures A and B

Orders

  • The applicant is granted leave to rely upon the amended plans referred to in Condition 1 of Annexure 'A'.
  • The Appeal is upheld.