Bilal El Samman v Sutherland Shire Council [2017] NSWLEC 1637
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were disposed of in accordance with that agreement by upholding the appeal and approving the s95A application.
- Jurisdiction
- Australia
- Judgment Date
- 10 November 2017
- Procedural Posture
- Class 1 Development Application Appeal / Conciliation Conference; Orders Made by Agreement Under S 34(3) of the Land and Environment Court Act 1979
- Outcome
- Appeal upheld; s95A application approved.
- Legal Topics
- ['conciliation Conference' 'agreement Between Parties' 'deferred Commencement Conditions' 'extension of Time for Development Consent Conditions']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 1 Development Application Appeal / Conciliation Conference; Orders Made by Agreement Under S 34(3) of the Land and Environment Court Act 1979
Legal Issues
- 1 ["Whether the Court should dispose of the proceedings in accordance with the parties' agreement under s 34(3) of the Land and Environment Court Act 1979." 'Whether the s95A application dated 7 August 2017 seeking a one year extension to 20 January 2019 to satisfy deferred commencement conditions 1–5 for DA 15/0976 should be approved.']
Ratio Decidendi
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were disposed of in accordance with that agreement by upholding the appeal and approving the s95A application.
Court Disposition
Appeal upheld; s95A application approved.
Orders
- ['The appeal is upheld.' 'The s95A application dated 7 August 2017 seeking a one (1) year extension to 20 January 2019 to satisfy the deferred commencement conditions 1 – 5 for DA 15/0976 is approved and the updated conditions of consent are contained at annexure A.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment