Having heard scientific evidence about the need to protect future occupants from contaminated materials generated by remediation activities on the Lednez site, and relying on both parties' explanation of the operation of proposed conditions F1A to F1D, the Court accepted that granting the consent orders was appropriate.

Jurisdiction
Australia
Judgment Date
29 January 2010
Procedural Posture
Appeal Under S 75 W(5) of the Environmental Planning and Assessment Act 1979 Concerning a Request to Modify a Major Project Approval / Ex Tempore Judgment on Consent Orders
Outcome
Appeal upheld by consent; Major Project No. 05_0110 amended; no order as to costs.
Legal Topics
['modification of Major Project Approval' 'occupation Certificates' 'remediation Conditions' 'health Impacts From Contaminated Material' 'consent Orders']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Appeal Under S 75 W(5) of the Environmental Planning and Assessment Act 1979 Concerning a Request to Modify a Major Project Approval / Ex Tempore Judgment on Consent Orders

  1. 1 ['Whether condition F1 of Major Project No. 05_0110 should be modified to permit Occupation Certificates to issue before completion of remediation activities in Precinct B subject to conditions.' 'Whether the proposed replacement conditions adequately protected future occupants from potential health impacts from contaminated materials generated by remediation activities on the Lednez site.' 'Whether the consent orders deleting condition F1 and inserting conditions F1A, F1B, F1C and F1D were appropriate in the circumstances.']

Ratio Decidendi

Having heard scientific evidence about the need to protect future occupants from contaminated materials generated by remediation activities on the Lednez site, and relying on both parties' explanation of the operation of proposed conditions F1A to F1D, the Court accepted that granting the consent orders was appropriate.

Court Disposition

Appeal upheld by consent; Major Project No. 05_0110 amended; no order as to costs.

Orders

  • ['Appeal No 10667 of 2009 is upheld.' 'Major Project No. 05_0110 approved by the Minister of Planning on 13 November 2007, is amended in accordance with Annexure A.' 'No order as to costs' 'The exhibits are returned with the exception of exhibit 19.']