Boral Resources (NSW) Pty Ltd v Camden Council [2018] NSWLEC 1623
Development for the mobile concrete batching plant on Lot 100 is permissible with development consent under cl 7(4)(d) of the Mining SEPP as extractive industry is currently carried out lawfully on that land pursuant to extant consent; the variation to the building height standard in cl 4.3 of CLEP is justified and granted under cl 4.6, as the applicant's request adequately demonstrates lack of adverse amenity or visual impacts, the height is operationally necessary, and the objectives of both the control and the zone are satisfied. Acoustic and traffic impacts are within guideline thresholds with imposed conditions. Consent is in the public interest.
- Parties
- Applicant: Boral Resources (NSW) Pty Ltd; Respondent: Camden Council
- Jurisdiction
- Australia
- Judgment Date
- 05 December 2018
- Procedural Posture
- Development Application Appeal / Class 1 Merit Appeal; Final Judgment
- Outcome
- Appeal upheld; development consent granted, variation to building height standard granted
- Legal Topics
- Development Consent, Variation of Development Standards, Permissibility of Land Use, Environmental Impact Assessment, Building Height Controls, Noise and Acoustic Impacts, Visual Impact, Public Interest
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Boral Resources (NSW) Pty Ltd
Applicant
Camden Council
Respondent
Procedural Posture
Development Application Appeal / Class 1 Merit Appeal; Final Judgment
Legal Issues
- 1 Whether the proposed mobile concrete batching plant is permissible with development consent under cl 7(4)(d) of State Environmental Planning Policy (Mining, Petroleum Production and Extractive Industries) 2007
- 2 Whether the applicant's request to vary the height of buildings standard under cl 4.3 of Camden Local Environmental Plan 2010 should be granted under cl 4.6 of the instrument
- 3 Whether proposed development has acceptable amenity, visual, acoustic, and traffic impacts
Ratio Decidendi
Development for the mobile concrete batching plant on Lot 100 is permissible with development consent under cl 7(4)(d) of the Mining SEPP as extractive industry is currently carried out lawfully on that land pursuant to extant consent; the variation to the building height standard in cl 4.3 of CLEP is justified and granted under cl 4.6, as the applicant's request adequately demonstrates lack of adverse amenity or visual impacts, the height is operationally necessary, and the objectives of both the control and the zone are satisfied. Acoustic and traffic impacts are within guideline thresholds with imposed conditions. Consent is in the public interest.
Court Disposition
Appeal upheld; development consent granted, variation to building height standard granted
Orders
- The Applicant's written request to vary the height of the building development standard under cl 4.3 of Camden Local Environmental Plan 2010 is granted pursuant to the jurisdiction of the Court under cl 4.6 of that instrument.
- The appeal is upheld.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment