Brice & Ors v Biruski [2010] NSWDC 267
The defendant was in breach of contract and deed of variation due to failure to complete works within specified periods and to reasonable standard, and was not entitled to claimed extensions of time, nor to suspend work or retain further payment. Plaintiffs were entitled to terminate the contract and claim damages for completion and delay to the point of completion, but not for subsequent decline in property value as such loss was not within the contemplation of the parties at contract formation.
- Parties
- First Plaintiff and First Cross Defendant: James Patrick Brice; Second Plaintiff and Second Cross Defendant: Catherine Ann Brice; Defendant and Cross Claimant: Vlado Biruski
- Jurisdiction
- Australia
- Judgment Date
- 26 November 2010
- Procedural Posture
- Civil / Judgment on Liability and Adjournment for Assessment of Damages, Costs, and Interest; Later Consent Orders and Judgment for Cross Claimant
- Outcome
- Proceedings adjourned for assessment of damages, costs, and interest. Subsequent judgment for cross claimant by consent orders.
- Legal Topics
- Breach of Contract, Negligence, Delay in Completion, Assessment of Damages, Cross Claim, Termination of Contract
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
James Patrick Brice
First Plaintiff and First Cross Defendant
Catherine Ann Brice
Second Plaintiff and Second Cross Defendant
Vlado Biruski
Defendant and Cross Claimant
Procedural Posture
Civil / Judgment on Liability and Adjournment for Assessment of Damages, Costs, and Interest; Later Consent Orders and Judgment for Cross Claimant
Legal Issues
- 1 Whether the defendant breached the building contract and deed of variation
- 2 Whether the plaintiffs were entitled to terminate the contract
- 3 Whether the defendant was entitled to extensions of time or payment for variations
Ratio Decidendi
The defendant was in breach of contract and deed of variation due to failure to complete works within specified periods and to reasonable standard, and was not entitled to claimed extensions of time, nor to suspend work or retain further payment. Plaintiffs were entitled to terminate the contract and claim damages for completion and delay to the point of completion, but not for subsequent decline in property value as such loss was not within the contemplation of the parties at contract formation.
Court Disposition
Proceedings adjourned for assessment of damages, costs, and interest. Subsequent judgment for cross claimant by consent orders.
Orders
- Proceedings adjourned for calculation of damages to be paid to the plaintiffs and to deal with issues of costs and interest.
- Reasons published.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment