Balogh v Cardno (NSW/ACT) Pty Ltd [2021] NSWCATCD 102
Ms Balogh was not a party to the relevant building contract, which was exclusively between Genuine Building Solutions Pty Ltd and The Owners of Strata Plan No. 3755. As such, she could not claim delay damages under that contract against the named respondents.
- Jurisdiction
- Australia
- Judgment Date
- 15 October 2021
- Procedural Posture
- Home Building Claim (delay Damages) / Principal Judgment Final Determination
- Outcome
- Application dismissed
- Legal Topics
- ['home Building Act 1989 (nsw)' 'contractual Breach' 'delay Damages' 'party to Contract' 'strata Schemes Management Act 2015 (nsw)']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Home Building Claim (delay Damages) / Principal Judgment Final Determination
Legal Issues
- 1 ['Whether Ms Balogh was a party to the building contract and entitled to claim delay damages under it' 'Whether any of the named respondents were in a contractual relationship with Ms Balogh to support the claim for delay damages' 'Whether the claim could alternatively be brought under statutory rights against the Owners Corporation']
Ratio Decidendi
Ms Balogh was not a party to the relevant building contract, which was exclusively between Genuine Building Solutions Pty Ltd and The Owners of Strata Plan No. 3755. As such, she could not claim delay damages under that contract against the named respondents.
Court Disposition
Application dismissed
Orders
- ['The application is dismissed.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment