CC Builders (Aust) Pty Ltd v Milestone Civil Pty Ltd [2019] NSWSC 1251
The Adjudicator's decision to exclude consideration of the Plaintiff's submissions on the Second EOT claim was irrational and without reasonable foundation as the payment schedule did include the claim. This constituted denial of procedural fairness and a jurisdictional error, justifying that part of the decision being quashed. No jurisdictional error was established in relation to the Carry Over claim. The Plaintiff is entitled to relief, subject to accepting conditions including liability for half of the Adjudicator's fees and not re-agitating the Carry Over claim except at final hearing.
- Parties
- Plaintiff: CC Builders (Aust) Pty Ltd; First Defendant: Milestone Civil Pty Ltd; Second Defendant: Robert Sundercombe
- Jurisdiction
- Australia
- Judgment Date
- 06 September 2019
- Procedural Posture
- Proceedings Commenced by Summons and Technology and Construction List Statement / Judgment Following Hearing
- Outcome
- Complaint in relation to Second EOT claim upheld; Adjudicator's decision on this issue quashed; remainder of determination upheld; Plaintiff to accept liability for half of Adjudicator's fees, subject to conditions to be set; parties to be heard on form of orders and costs.
- Legal Topics
- Security of Payment, Procedural Fairness, Jurisdictional Error, Adjudicator's Fees
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
CC Builders (Aust) Pty Ltd
Plaintiff
Milestone Civil Pty Ltd
First Defendant
Robert Sundercombe
Second Defendant
Procedural Posture
Proceedings Commenced by Summons and Technology and Construction List Statement / Judgment Following Hearing
Legal Issues
- 1 Whether the Adjudicator denied the Plaintiff natural justice and procedural fairness by failing to consider Plaintiff's submissions on the Second EOT claim
- 2 Whether the Adjudicator made a jurisdictional error in relation to the Carry Over claim
- 3 Appropriate disposition of Adjudicator's fees under the Act
Ratio Decidendi
The Adjudicator's decision to exclude consideration of the Plaintiff's submissions on the Second EOT claim was irrational and without reasonable foundation as the payment schedule did include the claim. This constituted denial of procedural fairness and a jurisdictional error, justifying that part of the decision being quashed. No jurisdictional error was established in relation to the Carry Over claim. The Plaintiff is entitled to relief, subject to accepting conditions including liability for half of the Adjudicator's fees and not re-agitating the Carry Over claim except at final hearing.
Court Disposition
Complaint in relation to Second EOT claim upheld; Adjudicator's decision on this issue quashed; remainder of determination upheld; Plaintiff to accept liability for half of Adjudicator's fees, subject to conditions to be set; parties to be heard on form of orders and costs.
Orders
- The Adjudicator's decision in relation to the Second EOT claim is quashed, subject to conditions.
- No error demonstrated on the Carry Over claim and no error of jurisdictional kind identified.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment