Summers v Commonwealth [1919] HCA 20

Summers v Commonwealth [1919] HCA 20

The contract obliges the supplier to provide blocks matching the specified dimensions in the schedule, each eligible to be worked into a single piece as specified, not larger blocks from which multiple pieces could be cut.

Parties
Plaintiff: Charles Francis Summers; Defendant: The Commonwealth
Jurisdiction
Australia
Judgment Date
15 May 1919
Procedural Posture
Contract Appeal / High Court Appeal
Outcome
appeal dismissed with costs
Legal Topics
Construction of Building Contracts, Interpretation of Supply Specifications

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 2 Authorities cited 1 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Parties

Charles Francis Summers

Plaintiff

The Commonwealth

Defendant

Procedural Posture

Contract Appeal / High Court Appeal

  1. 1 Whether the contract entitled Summers to supply large blocks from which multiple scheduled pieces could be cut, or only single-piece blocks matching the schedule dimensions.

Ratio Decidendi

The contract obliges the supplier to provide blocks matching the specified dimensions in the schedule, each eligible to be worked into a single piece as specified, not larger blocks from which multiple pieces could be cut.

Court Disposition

appeal dismissed with costs

Orders

  • Appeal dismissed with costs.