Co-ordinated Construction Co Pty Limited v Climatech (Canberra) Pty Ltd [2005] NSWSC 312
Delay damages claimed consequent upon extensions of time are not variations under the contract, but may properly be included in progress claims as 'other monies' due under the contract provisions, and are able to be claimed as 'related services' under the Act; error by the adjudicator in construing these as variations does not render the determination void as the basic and essential requirements of the Act were substantially complied with, and thus the plaintiff is not entitled to injunctive relief.
- Jurisdiction
- Australia
- Judgment Date
- 13 April 2005
- Procedural Posture
- Application for Permanent Injunction / Judgment
- Outcome
- Summons dismissed
- Legal Topics
- ['statutory Construction' 'security of Payment' 'injunctions' 'delay Damages' 'extensions of Time' 'variations in Construction Contracts']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Application for Permanent Injunction / Judgment
Legal Issues
- 1 ['Whether delay damages consequential upon extensions of time can be claimed in a payment claim under the Building and Construction Industry Security of Payment Act 1999 (NSW)' "Whether the claims under the contract as a result of the awarding of extensions of time were 'variation' claims under the contract" "Whether the adjudicator's determination was void for failure to comply with basic and essential requirements of the Act"]
Ratio Decidendi
Delay damages claimed consequent upon extensions of time are not variations under the contract, but may properly be included in progress claims as 'other monies' due under the contract provisions, and are able to be claimed as 'related services' under the Act; error by the adjudicator in construing these as variations does not render the determination void as the basic and essential requirements of the Act were substantially complied with, and thus the plaintiff is not entitled to injunctive relief.
Court Disposition
Summons dismissed
Orders
- ['Summons dismissed' 'No declaration or certiorari granted' 'Costs reserved for argument if parties do not agree']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment