CP Pymble Developments Pty Ltd v Ku KIng Gai Council [2015] NSWLEC 1492

CP Pymble Developments Pty Ltd v Ku KIng Gai Council [2015] NSWLEC 1492

The Court is required to make orders disposing of proceedings in accordance with an agreement reached under s 34(3) if satisfied that the decision is one the Court could have made.

Parties
Applicant: CP Pymble Developments Pty Ltd; Respondent: Ku-ring-gai Municipal Council
Jurisdiction
Australia
Judgment Date
24 November 2015
Procedural Posture
Class 1 / Post Conciliation Conference Agreement and Orders
Outcome
Proceedings disposed of by consent orders reflecting parties' agreement under s 34(3) of Land and Environment Court Act 1979
Legal Topics
Modification Application, Demolition, Residential Flat Building Construction, Deep Soil Area, Tree Removal, Pedestrian Path, Conciliation Conference, Court Orders Under S 34 of Land and Environment Court Act

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 3 Party arguments 1
Sign in to unlock

Parties

CP Pymble Developments Pty Ltd

Applicant

Ku-ring-gai Municipal Council

Respondent

Procedural Posture

Class 1 / Post Conciliation Conference Agreement and Orders

  1. 1 Whether the agreement reached at conciliation conference should be made the determination of the Court under s 34(3) of the Land and Environment Court Act 1979

Ratio Decidendi

The Court is required to make orders disposing of proceedings in accordance with an agreement reached under s 34(3) if satisfied that the decision is one the Court could have made.

Court Disposition

Proceedings disposed of by consent orders reflecting parties' agreement under s 34(3) of Land and Environment Court Act 1979

Orders

  • Orders made to give effect to the agreement were issued on 24 November 2015; copy accessible as annexed documents