Keogh v CPB Contractors Pty Ltd & Ors (No 4) [2024] NSWDDT 12
Section 151S(2) of the Workers Compensation Act 1987 (NSW) does not apply in circumstances where there are separate assessments against successive tortfeasors rather than joint tortfeasors and no declaration as to s 151S(1) has been made; the conventional apportionment of costs between tortfeasors suffices.
- Parties
- Plaintiff: Craig Andrew Keogh; Third Defendant: Downer EDI Mining Pty Ltd; Fifth Defendant: Downer Mining Regional (NSW) Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 16 October 2024
- Procedural Posture
- Procedural Ruling / Post Judgment Costs Variation Application
- Outcome
- Application dismissed; costs ordered against the fifth defendant
- Legal Topics
- Apportionment of Costs, Section 151 S Workers Compensation Act 1987 (nsw), Contribution Between Tortfeasors
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Craig Andrew Keogh
Plaintiff
Downer EDI Mining Pty Ltd
Third Defendant
Downer Mining Regional (NSW) Pty Ltd
Fifth Defendant
Procedural Posture
Procedural Ruling / Post Judgment Costs Variation Application
Legal Issues
- 1 Whether costs awarded should be apportioned pursuant to s 151S(2) of the Workers Compensation Act 1987 (NSW)
- 2 Whether s 151S applies in circumstances of separate assessments against successive tortfeasors
Ratio Decidendi
Section 151S(2) of the Workers Compensation Act 1987 (NSW) does not apply in circumstances where there are separate assessments against successive tortfeasors rather than joint tortfeasors and no declaration as to s 151S(1) has been made; the conventional apportionment of costs between tortfeasors suffices.
Court Disposition
Application dismissed; costs ordered against the fifth defendant
Orders
- Dismiss the application based upon s 151S of the Workers Compensation Act 1987 (NSW), made by the fifth defendant, for a variation of the existing costs orders.
- Order the fifth defendant to pay the costs of the plaintiff and the third defendant (re the Boggabri Mine) of and incidental to the application.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment