C & V Engineering Services Pty Ltd v Metropolitan Demolitions Pty Ltd (No. 4) [2023] NSWDC 483
C&V failed to prove entitlement to claim damages for work performed after 27 July 2018 on the Building C contract, as work done after Metropolitan's direction was not caused by breach, and C&V deliberately continued despite knowing work was not requested. The chain of causation was broken; C&V's continued work was a free and informed act outside the scope of recoverable damages.
- Parties
- Plaintiff: C&V Engineering Services Pty Ltd; Defendant: Metropolitan Demolitions Pty Limited
- Jurisdiction
- Australia
- Judgment Date
- 10 November 2023
- Procedural Posture
- Civil / Assessment of Damages on Remitter After Appeal
- Outcome
- Judgment for the plaintiff in a reduced sum; damages assessed only to 27 July 2018; interest and costs orders as qualified in the reasons.
- Legal Topics
- Assessment of Damages, Breach of Contract, Repudiation, Mitigation of Loss, Causation
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
C&V Engineering Services Pty Ltd
Plaintiff
Metropolitan Demolitions Pty Limited
Defendant
Procedural Posture
Civil / Assessment of Damages on Remitter After Appeal
Legal Issues
- 1 Is C&V entitled to damages in respect to works done under the Building C contract after 27 July 2018?
- 2 What is the quantum of loss for breach of the contract?
- 3 What are the appropriate final orders?
Ratio Decidendi
C&V failed to prove entitlement to claim damages for work performed after 27 July 2018 on the Building C contract, as work done after Metropolitan's direction was not caused by breach, and C&V deliberately continued despite knowing work was not requested. The chain of causation was broken; C&V's continued work was a free and informed act outside the scope of recoverable damages.
Court Disposition
Judgment for the plaintiff in a reduced sum; damages assessed only to 27 July 2018; interest and costs orders as qualified in the reasons.
Orders
- Referee's report of 28 September 2023 adopted as necessary.
- Judgment for the plaintiff on the Building C contract for $45,713.12.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment