Symond v Dovera Homes Pty Ltd [2025] NSWCATAP 19
The Tribunal at first instance erred in calculating damages as if the cost of completion covered all contract works; the evidence showed the cost of completion was only to lock-up stage. The appropriate assessment is damages for the cost to reach lock-up stage plus rectification, less the unpaid balance to that...
Source-derived case information.
- Parties
- Appellant: Daniel William Symond; Appellant: Petra Deanne Symond; Respondent: Dovera Homes Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 04 February 2025
- Procedural Posture
- Appeal / Appeal Panel Decision
- Outcome
- Appeal allowed
- Legal Topics
- Damages Assessment, Appeal Procedure, Calculation of Damages
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Daniel William Symond
Appellant
Petra Deanne Symond
Appellant
Dovera Homes Pty Ltd
Respondent
Procedural Posture
Appeal / Appeal Panel Decision
Legal Issues
- 1 Whether the method used to calculate damages at first instance was correct
- 2 Whether the amount of damages awarded was correct
Ratio Decidendi
The Tribunal at first instance erred in calculating damages as if the cost of completion covered all contract works; the evidence showed the cost of completion was only to lock-up stage. The appropriate assessment is damages for the cost to reach lock-up stage plus rectification, less the unpaid balance to that stage, plus expenses.
Court Disposition
Appeal allowed
Orders
- Leave to appeal is granted.
- The appeal is allowed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment