DCP Developments Pty Ltd v Inner West Council [2016] NSWLEC 1325

DCP Developments Pty Ltd v Inner West Council [2016] NSWLEC 1325

The Court made orders by consent under s 34(3) of the Land and Environment Court Act 1979, disposing of the proceedings in accordance with the parties' agreement.

Jurisdiction
Australia
Judgment Date
08 August 2016
Procedural Posture
Development Application Appeal / Post Conciliation Conference; Final Orders by Consent
Outcome
Appeal upheld by consent; development application approved with conditions by agreement under s 34(3) of the Land and Environment Court Act 1979.
Legal Topics
['development Application' 'conciliation Conference' 'section 34 Agreement']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 1 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Development Application Appeal / Post Conciliation Conference; Final Orders by Consent

  1. 1 ['Whether the Court should make orders by consent under s 34(3) of the Land and Environment Court Act 1979 following agreement between parties']

Ratio Decidendi

The Court made orders by consent under s 34(3) of the Land and Environment Court Act 1979, disposing of the proceedings in accordance with the parties' agreement.

Court Disposition

Appeal upheld by consent; development application approved with conditions by agreement under s 34(3) of the Land and Environment Court Act 1979.

Orders

  • ["The applicant is granted leave to amend Development Application DA 2015/00484 in accordance with the plans and documentation set out in condition 3 of the conditions annexed at 'A' to this agreement." 'The appeal is upheld.' "Development Application DA 2015/00484 for the demolition of existing improvements and the...