Dewu Pty Ltd v Fabiano [2014] NSWSC 943
Even if the adjudicator erred in construing the contract to include the 'Scheduled Payment' document, such an error is within jurisdiction and does not invalidate the determination. The conclusion that the 'Scheduled Payment' formed part of the contract was open to the adjudicator and correct on the evidence.
- Jurisdiction
- Australia
- Judgment Date
- 14 July 2014
- Procedural Posture
- Application to Quash Adjudication Determination / Final Judgment
- Outcome
- Application dismissed
- Legal Topics
- ['adjudication Applications' 'jurisdictional Error' 'construction Contracts' 'security of Payment Act']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Application to Quash Adjudication Determination / Final Judgment
Legal Issues
- 1 ['Whether the adjudicator made an error within jurisdiction' 'Whether the adjudicator erred in determining the terms of the construction contract' 'Whether an error as to the terms, construction or application of a construction contract is a jurisdictional error']
Ratio Decidendi
Even if the adjudicator erred in construing the contract to include the 'Scheduled Payment' document, such an error is within jurisdiction and does not invalidate the determination. The conclusion that the 'Scheduled Payment' formed part of the contract was open to the adjudicator and correct on the evidence.
Court Disposition
Application dismissed
Orders
- ['The originating process filed 4 December 2013 is dismissed with costs.' 'Exhibits are to be handed out once the revised version of these reasons has been made available to the parties.' "Liberty to apply reserved on three days' notice."]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment