DM & BP Wiskich Pty Ltd v Boral Bricks Pty Ltd [2012] NSWDC 145
Because the related proceedings established Boral's responsibility for Mr Cosmidis's injuries, with no contributory negligence by Mr Cosmidis and no negligence by the employer, and because the compensation amount was not disputed, the plaintiff was entitled to judgment for the compensation payments plus interest.
- Jurisdiction
- Australia
- Judgment Date
- 13 September 2012
- Procedural Posture
- Civil Claim in Negligence for Recovery of Workers' Compensation Payments Under S 151 Z(1)(d) of the Workers' Compensation Act 1987 / Principal Judgment
- Outcome
- Verdict and judgment for the plaintiff against the defendant in the sum of $251,859.13 including interest to the date of judgment.
- Legal Topics
- ['negligence' 'subrogated Claim by Employer' "recovery of Workers' Compensation Payments" 'interest on Damages' 'costs']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Civil Claim in Negligence for Recovery of Workers' Compensation Payments Under S 151 Z(1)(d) of the Workers' Compensation Act 1987 / Principal Judgment
Legal Issues
- 1 ["Whether the plaintiff employer was entitled under s 151Z(1)(d) of the Workers' Compensation Act 1987 to recover workers' compensation payments made to its employee from the defendant tortfeasor." 'Whether the plaintiff was entitled to interest on the recovery amount to the date of judgment.']
Ratio Decidendi
Because the related proceedings established Boral's responsibility for Mr Cosmidis's injuries, with no contributory negligence by Mr Cosmidis and no negligence by the employer, and because the compensation amount was not disputed, the plaintiff was entitled to judgment for the compensation payments plus interest.
Court Disposition
Verdict and judgment for the plaintiff against the defendant in the sum of $251,859.13 including interest to the date of judgment.
Orders
- ['Verdict and judgment for the plaintiff DM & BP Wiskich Pty Ltd against the defendant, Boral Bricks Pty Limited, in the sum of $251,859.13 including interest to the date of judgment.' "The defendant, Boral Bricks Pty Limited, is to pay the plaintiff's costs of the proceedings on the ordinary basis, unless otherwise...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment