Schmuelly v Elrob Construction Group Pty Ltd (No 3) [2025] NSWSC 118
The builder did not engage in misleading or deceptive conduct as alleged; the statements about building experience were not relied upon or not shown to be misleading. The works were incomplete and defective, but the plaintiff was not entitled to recover completion costs as he did not prove builder's repudiation. The plaintiff was entitled to recover overpayments made for incomplete milestone payments and overcharged variations, as the builder received more than the value of works done. The builder's cross-claim for unpaid variations and quantum meruit failed, as he had already been overpaid.
- Parties
- Plaintiff: Dror Schmuelly; First Defendant: Elrob Construction Group Pty Ltd; Second Defendant: Elia Boujaoude
- Jurisdiction
- Australia
- Judgment Date
- 06 March 2025
- Procedural Posture
- Principal Judgment / Final Determination After Trial
- Outcome
- Judgment for plaintiff in part; claim and cross-claim otherwise dismissed.
- Legal Topics
- Misleading or Deceptive Conduct, Building Contracts, Repudiation, Rectification of Defects, Damages Assessment, Milestone Payments, Variations, Mitigation of Loss
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Dror Schmuelly
Plaintiff
Elrob Construction Group Pty Ltd
First Defendant
Elia Boujaoude
Second Defendant
Procedural Posture
Principal Judgment / Final Determination After Trial
Legal Issues
- 1 Whether the builder engaged in misleading or deceptive conduct regarding prior experience
- 2 Whether the builder breached the building contract
- 3 Whether the builder repudiated the contract
Ratio Decidendi
The builder did not engage in misleading or deceptive conduct as alleged; the statements about building experience were not relied upon or not shown to be misleading. The works were incomplete and defective, but the plaintiff was not entitled to recover completion costs as he did not prove builder's repudiation. The plaintiff was entitled to recover overpayments made for incomplete milestone payments and overcharged variations, as the builder received more than the value of works done. The builder's cross-claim for unpaid variations and quantum meruit failed, as he had already been overpaid.
Court Disposition
Judgment for plaintiff in part; claim and cross-claim otherwise dismissed.
Orders
- Judgment for the plaintiff against the first defendant in the sum of $1,133,332 (excluding GST) together with interest under s 100 of the Civil Procedure Act 2005 (NSW).
- Proceedings otherwise dismissed.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment