East End Projects Pty Ltd v GJ Building and Contracting Pty Ltd [2020] NSWSC 819
The requirement that GJBC serve a draft progress claim on or before the 25th day of the month meant that, if it failed to do so, no reference date arose and it lost the right to make a progress claim for that month. That contingency seriously restricted the operation of s 8 of the Act and was not merely facilitative. The Contract therefore did not identify a valid date on which a progress payment claim could be made, so a statutory reference date arose under s 8(2), and East End was not entitled to the declaration or injunction sought.
- Jurisdiction
- Australia
- Judgment Date
- 29 June 2020
- Procedural Posture
- Summons Seeking Declaratory and Injunctive Relief Concerning a Payment Claim Under the Building & Construction Industry Security of Payment Act 1999 (nsw) / Principal Judgment
- Outcome
- Summons dismissed with costs.
- Legal Topics
- ['progress Payments' 'payment Claims' 'reference Dates' 'validity of Contractual Provisions Restricting the Operation of the Building & Construction Industry Security of Payment Act 1999 (nsw)']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Summons Seeking Declaratory and Injunctive Relief Concerning a Payment Claim Under the Building & Construction Industry Security of Payment Act 1999 (nsw) / Principal Judgment
Legal Issues
- 1 ["Whether a reference date had arisen in respect of GJBC's payment claim dated 28 May 2020 when it was served." 'Whether the contractual mechanism requiring a draft progress claim by the 25th day of the month was void under s 34 of the Building & Construction Industry Security of Payment Act 1999 (NSW) because it restricted the operation of the Act.' 'Whether the absence of a draft progress claim meant that no relevant reference date had arisen under the Contract.']
Ratio Decidendi
The requirement that GJBC serve a draft progress claim on or before the 25th day of the month meant that, if it failed to do so, no reference date arose and it lost the right to make a progress claim for that month. That contingency seriously restricted the operation of s 8 of the Act and was not merely facilitative. The Contract therefore did not identify a valid date on which a progress payment claim could be made, so a statutory reference date arose under s 8(2), and East End was not entitled to the declaration or injunction sought.
Court Disposition
Summons dismissed with costs.
Orders
- ['Summons be dismissed with costs.']
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment