EDE Excavations Pty Ltd v Lake Macquarie City Council [2008] NSWDC 281
The Council breached the contract by failing to follow the contractually required procedures for termination and dispute resolution; this amounted to repudiation and wrongful termination, and the Council is liable for damages.
Source-derived case information.
- Parties
- Plaintiff: EDE Excavations Pty Ltd; Defendant: Lake Macquarie City Council
- Jurisdiction
- Australia
- Judgment Date
- 14 November 2008
- Procedural Posture
- Contract / Liability Trial
- Outcome
- Found against Defendant on liability
- Legal Topics
- Wrongful Termination, Repudiation, Procedural Obligations, Good Faith and Fair Dealing
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
EDE Excavations Pty Ltd
Plaintiff
Lake Macquarie City Council
Defendant
Procedural Posture
Contract / Liability Trial
Legal Issues
- 1 Did the Council wrongfully terminate the contract?
- 2 Was the contract repudiated by the Council's conduct?
- 3 Did the plaintiff commit fraud by submitting false timesheets?
Ratio Decidendi
The Council breached the contract by failing to follow the contractually required procedures for termination and dispute resolution; this amounted to repudiation and wrongful termination, and the Council is liable for damages.
Court Disposition
Found against Defendant on liability
Orders
- Council liable to plaintiff for damages for breach of contract and wrongful termination.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment