Benjamin & Benjamin v Geneville Constructions Pty Ltd [2022] NSWSC 982

Benjamin & Benjamin v Geneville Constructions Pty Ltd [2022] NSWSC 982

The Court found no jurisdictional error or substantial miscarriage of justice by the Appeal Panel: clause 14.7 broadly entitles the builder to claim for pre-contractual works and non-refundable costs (including undelivered custom windows and temporary fencing) when owners terminate a contract, and the absence of a...

Source-derived case information.

Jurisdiction
Australia
Judgment Date
27 July 2022
Procedural Posture
Application for Judicial Review and Extension of Time/leave to Appeal From Tribunal Decision / Supreme Court Final Judgment
Outcome
Application dismissed; costs ordered against plaintiffs
Legal Topics
['judicial Review of Tribunal Decisions' 'leave to Appeal' 'construction of Contractual Clauses' 'home Building Disputes' 'pre Contractual Work Compensation']
['administrative Law' 'contract Law' 'civil Procedure'] ['judicial Review of Tribunal Decisions' 'leave to Appeal' 'construction of Contractual Clauses' 'home Building Disputes' 'pre Contractual Work Compensation']

Source-derived case record

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Application for Judicial Review and Extension of Time/leave to Appeal From Tribunal Decision / Supreme Court Final Judgment

  1. 1 ['Whether the Appeal Panel erred in upholding claims for pre-contractual work in the absence of a contract' 'Whether the Appeal Panel erred in upholding claims for the cost of windows not delivered to the owners' 'Whether the Appeal Panel erred in upholding charges for temporary fencing based on third-party invoices' "Whether any jurisdictional error or miscarriage of justice occurred warranting exercise of the Court's supervisory jurisdiction"]

Ratio Decidendi

The Court found no jurisdictional error or substantial miscarriage of justice by the Appeal Panel: clause 14.7 broadly entitles the builder to claim for pre-contractual works and non-refundable costs (including undelivered custom windows and temporary fencing) when owners terminate a contract, and the absence of a temporal restriction allows recovery for works performed preparatory to execution; applicants' delay and lack of merit did not warrant judicial review or extension of time to appeal.

Court Disposition

Application dismissed; costs ordered against plaintiffs

Orders

  • ['The Summons filed on 16 August 2021 is dismissed.' "The plaintiffs are to pay the first defendant's costs of these proceedings."]