Towzell v Waverley Council [2015] NSWLEC 1511
As agreement was reached between the parties at or after a conciliation conference and the Commissioner was satisfied the decision is one the Court could have made in exercise of its functions, orders were made disposing of the proceedings in accordance with s 34(3) of the Land and Environment Court Act 1979.
- Jurisdiction
- Australia
- Judgment Date
- 07 December 2015
- Procedural Posture
- Development Application / Post Conciliation Conference; Final Orders
- Outcome
- Orders made to give effect to agreement between the parties under s 34(3) of the Land and Environment Court Act 1979
- Legal Topics
- ['development Application' 'section 34 Agreement' 'conciliation']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Development Application / Post Conciliation Conference; Final Orders
Legal Issues
- 1 ['Whether the agreement reached at conciliation conference could be made as an order of the Court under s 34(3) of the Land and Environment Court Act 1979']
Ratio Decidendi
As agreement was reached between the parties at or after a conciliation conference and the Commissioner was satisfied the decision is one the Court could have made in exercise of its functions, orders were made disposing of the proceedings in accordance with s 34(3) of the Land and Environment Court Act 1979.
Court Disposition
Orders made to give effect to agreement between the parties under s 34(3) of the Land and Environment Court Act 1979
Orders
- ["Final orders made in terms of parties' agreement at conciliation conference, as set out in the written orders dated 7 December 2015"]
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment