Mesiti v Northern Beaches Council [2016] NSWLEC 1448
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Acting Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were disposed of in accordance with the agreed orders.
Source-derived case information.
- Jurisdiction
- Australia
- Judgment Date
- 06 June 2016
- Procedural Posture
- Class 1 Building Certificate Proceedings / Orders Made After Conciliation Conference by Agreement Under S 34(3) of the Land and Environment Court Act 1979
- Outcome
- Appeal upheld; respondent to issue a building certificate after compliance with agreed conditions; respondent's name changed from Warringah Council to Northern Beaches Council.
- Legal Topics
- ['building Certificate' 'unauthorised Retaining Wall' 'structural Safety' 'pedestrian Safety' 'encroachment on Council Land' 'conciliation Conference' 'agreement Between the Parties']
Source-derived case record
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 1 Building Certificate Proceedings / Orders Made After Conciliation Conference by Agreement Under S 34(3) of the Land and Environment Court Act 1979
Legal Issues
- 1 ["Whether orders should be made to give effect to the parties' agreement under s 34(3) of the Land and Environment Court Act 1979 concerning issue of a building certificate for the retaining wall adjacent to 30 Pine Avenue, Narraweena."]
Ratio Decidendi
Because the parties reached an agreement under s 34(3) of the Land and Environment Court Act 1979 and the Acting Commissioner was satisfied that the agreed decision was one the Court could have made in the proper exercise of its functions, the proceedings were disposed of in accordance with the agreed orders.
Court Disposition
Appeal upheld; respondent to issue a building certificate after compliance with agreed conditions; respondent's name changed from Warringah Council to Northern Beaches Council.
Orders
- ['The appeal is upheld.' 'Following compliance with the conditions set out in Annexure "A" to the satisfaction of the respondent, the Respondent is to issue the Applicant with a building certificate for the retaining wall adjacent to 30 Pine Avenue, Narraweena by 31 January 2017.' 'The conditions set out in Annexure...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment