Forte Sydney Carlingford Development Pty Limited v Forte Sydney Carlingford Pty Limited [2024] FCAFC 9

Forte Sydney Carlingford Development Pty Limited v Forte Sydney Carlingford Pty Limited [2024] FCAFC 9

The Court held that the primary judge's orders were not attended by sufficient doubt to warrant reconsideration nor was there a risk of substantial injustice if leave were refused. The adjudicator's determination that there was no construction contract was a valid determination for the purposes of s 22 of the SOP Act, and any assertion of jurisdictional error should be determined by the court and not by the claimant unilaterally. Repetitive adjudication applications on the same claim constitute an abuse of process. The interim orders were a proper exercise of discretion.

Jurisdiction
Australia
Judgment Date
16 February 2024
Procedural Posture
Application for Leave to Appeal / Judgment on Application for Leave to Appeal
Outcome
Application for leave to appeal dismissed
Legal Topics
['security of Payment' 'interlocutory Injunctions' 'abuse of Process']

Case Brief

Summary, issues, holding and outcome

More case intelligence is available

Unlock the full research layer for this judgment.

Full judgment text Downloadable case file Legal principles 1 Authorities cited 2 Party arguments 2 Amounts and remedies 1
Sign in to unlock

Procedural Posture

Application for Leave to Appeal / Judgment on Application for Leave to Appeal

  1. 1 ["Whether the primary judge's restraining orders preventing adjudication under the Building and Construction Industry Security of Payment Act 1999 (NSW) should be reconsidered on appeal" "Whether the adjudicator's determination was vitiated by jurisdictional error and could thus be ignored or was valid for the purposes of the Act" 'Whether there was an abuse of process by submitting repeated adjudication applications under the Act based on the same payment claim' 'Interpretation and application of s 7(3)(c)(iii) and s 26(1) of the Security of Payment Act']

Ratio Decidendi

The Court held that the primary judge's orders were not attended by sufficient doubt to warrant reconsideration nor was there a risk of substantial injustice if leave were refused. The adjudicator's determination that there was no construction contract was a valid determination for the purposes of s 22 of the SOP Act, and any assertion of jurisdictional error should be determined by the court and not by the claimant unilaterally. Repetitive adjudication applications on the same claim constitute an abuse of process. The interim orders were a proper exercise of discretion.

Court Disposition

Application for leave to appeal dismissed

Orders

  • ['The application for leave to appeal is dismissed.' "The applicant is to pay the first respondent's costs."]