Kratz v East Coast Formwork & Concrete Pty Ltd [2016] NSWCATCD 94
The Tribunal found the trade contractor in substantial breach of contract for defective work on concrete columns following valid default notices and directions under the contract. Because only some rectification costs met the proper contractual procedure (incurred after default notices were received), the applicant could recover those, together with certain completion costs, but not broader damages for misleading conduct or pre-notice rectification. Only Frederick Kratz’s claim against East Coast Formwork & Concrete Pty Ltd succeeded in part; other applicant claims were dismissed for want of standing or lack of contractual privity.
- Jurisdiction
- Australia
- Judgment Date
- 23 November 2016
- Procedural Posture
- Building Claim / Final Decision
- Outcome
- Applicant Frederick Kratz succeeds in part; other claims dismissed. Monetary orders for rectification and completion costs. Procedure for subsequent costs applications set.
- Legal Topics
- ['defective Work' 'rectification Costs' 'termination of Contract' 'misleading and Deceptive Conduct' 'home Building Act Warranties' 'service of Directions']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Building Claim / Final Decision
Legal Issues
- 1 ['Whether claims for defects, incomplete work, and misleading conduct are established under contract and statute' 'Whether contractual procedures for termination and rectification were complied with' 'Whether notices of default were validly served' 'Whether damages are payable for defective and incomplete works, and if so, quantum']
Ratio Decidendi
The Tribunal found the trade contractor in substantial breach of contract for defective work on concrete columns following valid default notices and directions under the contract. Because only some rectification costs met the proper contractual procedure (incurred after default notices were received), the applicant could recover those, together with certain completion costs, but not broader damages for misleading conduct or pre-notice rectification. Only Frederick Kratz’s claim against East Coast Formwork & Concrete Pty Ltd succeeded in part; other applicant claims were dismissed for want of standing or lack of contractual privity.
Court Disposition
Applicant Frederick Kratz succeeds in part; other claims dismissed. Monetary orders for rectification and completion costs. Procedure for subsequent costs applications set.
Orders
- ["Christine Kratz's claim against East Coast Formwork & Concrete Pty Ltd and Mark Papadopoulos and Megan Louise Papadopoulos is dismissed." "Michael Kratz's claim against East Coast Formwork & Concrete Pty Ltd and Mark Papadopoulos and Megan Louise Papadopoulos is dismissed." 'East Coast Formwork & Concrete Pty Ltd...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment