Minas v Goulburn Mulwaree Council [2021] NSWLEC 1506
The Court determined that, as amended and conditioned by the parties' conciliation agreement, the proposed development and associated works satisfactorily addressed planning controls, flood risks, BCA requirements, and other matters relevant to the consent authority's functions. All jurisdictional prerequisites having been met, the Court was required to make orders granting development consent (with conditions) and directing the issue of a Building Information Certificate upon completion of the relevant works.
- Jurisdiction
- Australia
- Judgment Date
- 01 September 2021
- Procedural Posture
- Class 1 Planning Appeal and Building Information Certificate (bic) Appeal / Consent Orders Following Conciliation Conference
- Outcome
- Appeals upheld; development consent granted with conditions; Council directed to issue Building Information Certificate once conditions are satisfied.
- Legal Topics
- ['development Application Appeals' 'building Information Certificates' 'flooding Impact' 'environmental Planning Instruments' 'conciliation Agreements']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Class 1 Planning Appeal and Building Information Certificate (bic) Appeal / Consent Orders Following Conciliation Conference
Legal Issues
- 1 ['Whether development consent should be granted for alterations and additions to a residential flat building on flood prone land' 'Whether a Building Information Certificate should be issued for existing and modified works where Council refused both applications due to flood risk and non-compliance with building standards']
Ratio Decidendi
The Court determined that, as amended and conditioned by the parties' conciliation agreement, the proposed development and associated works satisfactorily addressed planning controls, flood risks, BCA requirements, and other matters relevant to the consent authority's functions. All jurisdictional prerequisites having been met, the Court was required to make orders granting development consent (with conditions) and directing the issue of a Building Information Certificate upon completion of the relevant works.
Court Disposition
Appeals upheld; development consent granted with conditions; Council directed to issue Building Information Certificate once conditions are satisfied.
Orders
- ['Court agrees to amendments to Development Application No. DA/0216/2021 as per conciliation agreement and referenced plan set.' 'Goulburn Mulwaree Council to lodge agreed amendments to DA on NSW planning portal within 14 days and notify applicant and Court.' 'Applicant to file copy of amended DA within 7 days after...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment