Drummond v Gordian Runoff Ltd (No 2) [2023] NSWSC 731
Indemnity costs were appropriate from the date of the offer of compromise as it involved a reasonable compromise (insurer forgoing costs) in a claim that was unlikely to succeed and all legal issues had been ventilated; however, rejection of the earlier Calderbank offer was not unreasonable given plaintiffs’ lack of awareness of key judicial decisions at the time and complexity of issues.
- Jurisdiction
- Australia
- Judgment Date
- 03 July 2023
- Procedural Posture
- Equity Technology and Construction List / Post Judgment (costs Order Following Primary Judgment)
- Outcome
- Plaintiffs to pay defendant's costs: on ordinary basis until 20 July 2022; indemnity basis thereafter (except for reply submissions dated 26 June 2023); no interest on costs.
- Legal Topics
- ['indemnity Costs' 'calderbank Offer' 'offer of Compromise' 'insurance Law' 'statutory Construction']
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Procedural Posture
Equity Technology and Construction List / Post Judgment (costs Order Following Primary Judgment)
Legal Issues
- 1 ['Entitlement to indemnity costs following rejection of Calderbank offer' 'Whether offer of compromise warrants indemnity costs' 'Application of section 54 of Insurance Contracts Act to section 103BB of Home Building Act' 'Effect of previous NCAT and District Court decisions on tribunal proceedings']
Ratio Decidendi
Indemnity costs were appropriate from the date of the offer of compromise as it involved a reasonable compromise (insurer forgoing costs) in a claim that was unlikely to succeed and all legal issues had been ventilated; however, rejection of the earlier Calderbank offer was not unreasonable given plaintiffs’ lack of awareness of key judicial decisions at the time and complexity of issues.
Court Disposition
Plaintiffs to pay defendant's costs: on ordinary basis until 20 July 2022; indemnity basis thereafter (except for reply submissions dated 26 June 2023); no interest on costs.
Orders
- ["Vary Order 2 made on 9 June 2023 such that the plaintiffs are to pay the defendant's costs on the ordinary basis until 20 July 2022." "Plaintiffs to pay defendant's costs on an indemnity basis thereafter, save and except for costs of the defendant's reply submissions dated 26 June 2023." 'No order for interest on...
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment