Hastie Group Limited (in liq) v Multiplex Constructions Pty Ltd (Formerly Brookfield Multiplex Constructions Pty Ltd) [2020] FCA 1824
Leave was granted to file and serve the Second Further Amended Originating Process, Points of Claim, and amended Concise Statements against Grocon and Watpac, as the claims were sufficiently identified in the original initiating documents and no relevant prejudice would result to respondents; costs of the separate and preliminary set-off question were ordered paid forthwith by applicants to respondents on a party-party basis, and leave to amend was conditioned on regularisation of pleadings and elimination of abandoned claims.
- Parties
- Applicant: Hastie Group Limited (in liquidation); Applicant: Craig David Crosbie (in his capacity as joint and several liquidator of the Hastie Group companies listed herein); Applicant: Ian Menzies Carson (in his capacity as joint and several liquidator of the Hastie Group companies listed herein); Applicant: David Laurence McEvoy (in his capacity as joint and several liquidator of the Hastie Group companies listed herein); Applicant: ACN 008 700 178 Pty Ltd (in liquidation) (formerly Direct Engineering Services Pty Ltd); Applicant: ACN 121 276 168 Pty Ltd (in liquidation) (formerly Heyday Group Pty Ltd); Applicant: ACN 129 953 733 Pty Limited (in liquidation) (formerly Beavis & Bartels Pty Ltd); Applicant: AFA Air Conditioning Pty Ltd (in liquidation); Applicant: Hastie Air Conditioning (ACT) Pty Ltd (in liquidation); Applicant: Hastie Air Conditioning Pty Ltd (in liquidation); Applicant: Hastie Australia Pty Ltd (in liquidation); Applicant: M&H Air Conditioning Pty Ltd (in liquidation); Applicant: Medical Gases Pty Ltd (in liquidation); Applicant: Nisbet & Durney Pty Ltd (in liquidation); Applicant: Norfolk Maintenance Holdings Pty Ltd (in liquidation); Applicant: Optimus Pty Ltd (in liquidation); Applicant: Sharp & Pendrey Pty Ltd (in liquidation); Applicant: Watters Electrical (Aust) Pty Ltd (in liquidation); Applicant: Airduster Pty Ltd (in liquidation); Applicant: ACN 050 411 179 Pty Ltd (in liquidation) (formerly Spectrum Fire & Security Pty Ltd); Respondent: Multiplex Constructions Pty Ltd (formerly Brookfield Multiplex Constructions Pty Ltd); Respondent: Brookfield Multiplex FSH Contractor Limited; Respondent: Lendlease Building Pty Limited (formerly Bovis Lend Lease Pty Ltd and Lend Lease Project Management & Construction (Australia) Pty Limited); Respondent: Lendlease Building Contractors Pty Limited (formerly Baulderstone Hornibrook Pty Ltd and Baulderstone Pty Ltd); Respondent: Lendlease Engineering Pty Limited (formerly Abigroup Contractors Pty Ltd); Respondent: Lendlease Funds Management Limited (formerly Lend Lease Funds Management Limited); Respondent: Badge Constructions (WA) Pty Ltd; Respondent: Badge Constructions (QLD) Pty Ltd; Respondent: Badge Constructions (SA) Pty Ltd; Respondent: CPB Contractors Pty Limited (formerly Leighton Contractors Pty Limited); Respondent: Grocon Constructors (NSW) Pty Ltd; Respondent: Grocon Constructors Pty Ltd; Respondent: Hansen Yuncken Pty Ltd; Respondent: John Holland Pty Ltd; Respondent: Laing O'Rourke Australia Construction Pty Ltd; Respondent: Thiess Pty Ltd; Respondent: Watpac Construction Pty Ltd (formerly Watpac Australia Pty Ltd and Watpac Construction (Qld) Pty Ltd); Respondent: Watpac Construction (NSW) Pty Ltd; Respondent: Watpac Construction (SA) Pty Ltd; Respondent: Watpac Construction (VIC) Pty Ltd; Respondent: Scentre Management Limited; Respondent: Scentre Design & Construction Pty Ltd
- Jurisdiction
- Australia
- Judgment Date
- 22 December 2020
- Procedural Posture
- Civil / Interlocutory Application for Leave to Amend Pleadings, Costs, and Procedural Orders
- Outcome
- Leave granted to applicants to file further amended pleadings, with conditions; costs of the separate and preliminary set-off question to be paid forthwith; further case management hearing adjourned.
- Legal Topics
- Amendment of Pleadings, Case Management, Joinder/removal of Parties, Costs, Cross Vesting/jurisdiction, Security of Payment
Case Brief
Summary, issues, holding and outcome
More case intelligence is available
Unlock the full research layer for this judgment.
Parties
Hastie Group Limited (in liquidation)
Applicant
Craig David Crosbie (in his capacity as joint and several liquidator of the Hastie Group companies listed herein)
Applicant
Ian Menzies Carson (in his capacity as joint and several liquidator of the Hastie Group companies listed herein)
Applicant
David Laurence McEvoy (in his capacity as joint and several liquidator of the Hastie Group companies listed herein)
Applicant
ACN 008 700 178 Pty Ltd (in liquidation) (formerly Direct Engineering Services Pty Ltd)
Applicant
ACN 121 276 168 Pty Ltd (in liquidation) (formerly Heyday Group Pty Ltd)
Applicant
ACN 129 953 733 Pty Limited (in liquidation) (formerly Beavis & Bartels Pty Ltd)
Applicant
AFA Air Conditioning Pty Ltd (in liquidation)
Applicant
Hastie Air Conditioning (ACT) Pty Ltd (in liquidation)
Applicant
Hastie Air Conditioning Pty Ltd (in liquidation)
Applicant
Hastie Australia Pty Ltd (in liquidation)
Applicant
M&H Air Conditioning Pty Ltd (in liquidation)
Applicant
Medical Gases Pty Ltd (in liquidation)
Applicant
Nisbet & Durney Pty Ltd (in liquidation)
Applicant
Norfolk Maintenance Holdings Pty Ltd (in liquidation)
Applicant
Optimus Pty Ltd (in liquidation)
Applicant
Sharp & Pendrey Pty Ltd (in liquidation)
Applicant
Watters Electrical (Aust) Pty Ltd (in liquidation)
Applicant
Airduster Pty Ltd (in liquidation)
Applicant
ACN 050 411 179 Pty Ltd (in liquidation) (formerly Spectrum Fire & Security Pty Ltd)
Applicant
Multiplex Constructions Pty Ltd (formerly Brookfield Multiplex Constructions Pty Ltd)
Respondent
Brookfield Multiplex FSH Contractor Limited
Respondent
Lendlease Building Pty Limited (formerly Bovis Lend Lease Pty Ltd and Lend Lease Project Management & Construction (Australia) Pty Limited)
Respondent
Lendlease Building Contractors Pty Limited (formerly Baulderstone Hornibrook Pty Ltd and Baulderstone Pty Ltd)
Respondent
Lendlease Engineering Pty Limited (formerly Abigroup Contractors Pty Ltd)
Respondent
Lendlease Funds Management Limited (formerly Lend Lease Funds Management Limited)
Respondent
Badge Constructions (WA) Pty Ltd
Respondent
Badge Constructions (QLD) Pty Ltd
Respondent
Badge Constructions (SA) Pty Ltd
Respondent
CPB Contractors Pty Limited (formerly Leighton Contractors Pty Limited)
Respondent
Grocon Constructors (NSW) Pty Ltd
Respondent
Grocon Constructors Pty Ltd
Respondent
Hansen Yuncken Pty Ltd
Respondent
John Holland Pty Ltd
Respondent
Laing O'Rourke Australia Construction Pty Ltd
Respondent
Thiess Pty Ltd
Respondent
Watpac Construction Pty Ltd (formerly Watpac Australia Pty Ltd and Watpac Construction (Qld) Pty Ltd)
Respondent
Watpac Construction (NSW) Pty Ltd
Respondent
Watpac Construction (SA) Pty Ltd
Respondent
Watpac Construction (VIC) Pty Ltd
Respondent
Scentre Management Limited
Respondent
Scentre Design & Construction Pty Ltd
Respondent
Procedural Posture
Civil / Interlocutory Application for Leave to Amend Pleadings, Costs, and Procedural Orders
Legal Issues
- 1 Whether leave should be granted to amend and file Second Further Amended Originating Process and Points of Claim
- 2 Whether costs thrown away should be taxed and paid forthwith and/or on indemnity basis
- 3 Whether certain respondents should be removed or claims discontinued
Ratio Decidendi
Leave was granted to file and serve the Second Further Amended Originating Process, Points of Claim, and amended Concise Statements against Grocon and Watpac, as the claims were sufficiently identified in the original initiating documents and no relevant prejudice would result to respondents; costs of the separate and preliminary set-off question were ordered paid forthwith by applicants to respondents on a party-party basis, and leave to amend was conditioned on regularisation of pleadings and elimination of abandoned claims.
Court Disposition
Leave granted to applicants to file further amended pleadings, with conditions; costs of the separate and preliminary set-off question to be paid forthwith; further case management hearing adjourned.
Orders
- Parties to confer and by 22 January 2021 file and serve agreed or separate minutes of orders and brief submissions.
- Further case management hearing adjourned to 29 January 2021 at 10.15am.
Full Case Text
Judgment text and source record
Sign in to read
Sign in to read the full judgment text
Sign in to read the full judgment text. Downloads and additional research tools may depend on your plan.
Sign in to read the full judgment